- Home
- State plan - 2021-22-JICA Scheme - Maint...
State plan - 2021-22-JICA Scheme - Maintenance of OHSR at Panavally and Perumbalam-Painting the OHSR at Panavally and Perumbalam
| Project |
State plan - 2021-22-JICA Scheme - Maintenance of OHSR at Panavally and Perumbalam-Painting the OHSR at Panavally and Perumbalam |
| Project Code |
ALPGOK06217650 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
State plan |
Type of scheme |
Water Supply |
| Description |
Painting the OHSR at Panavally and Perumbalam |
| Status |
On-going |
| District |
Alappuzha |
| Executing Office |
Alappuzha PH Dn |
| AS Amount (Rs) |
1400000
|
| AS Number |
KWA/JB/PIU-1/AE-4/AnnualPlan/2021-22(II) |
| TS Amount (Rs) |
1400000 |
| TS Number |
TS/2021-2022/2021/12477 |
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
Date is not specified |
| Coverage |
|
Packages
| No. |
Project Name |
Location |
View |
| 1 |
State plan - 2021-22-JICA Scheme - Maintenance of OHSR at Panavally and Perumbalam-Painting the OHSR at Panavally and Perumbalam |
Thycattsherry PH Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 24 Aug 2021 |
3rd extn notification done ; but single bid only
received. |
Thycattussery HW AEE |
|
| 05 Aug 2021 |
2nd extension notification up to 10/8/2021 |
Thycattussery HW AEE |
|
| 28 Jul 2021 |
Extended the date of tender to 2/8/2021and opening date on 6/8/2021 |
Thycattussery HW AEE |
|
| 25 Jul 2021 |
Tender opening date on 27/7/2021 |
Thycattussery HW AEE |
|
| 10 Jul 2021 |
TS Approved |
Alappuzha PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
Date is not specified |
| Scheduled date of Completion of the Project |
Date is not specified |
| Expected date of Completion |
31/12/2021 |
Processing Dates
| AS Date |
02 Jun 2021 |
| TS Date |
09 Jul 2021 |