Project | KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths-Package III(a) |
---|---|
Project Code | PTAKIIFB0117560P9 |
Type | Package |
Main Project | KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | This package includes Construction of 15 LL-OHSR at Thiruvanvandoor,,Laying pumping mains to Thiruvanvandoor,,Distribution for Thiruvanvandoor GP |
Status | On-going |
District | Pathanamthitta |
Executing Office | Adoor Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 91950000 |
TS Number | TS/2020-2021/2018/9295 Dated: 18-09-2020 |
Technical specification | This package includes Construction of 15 LL-OHSR at Thiruvanvandoor,,Laying pumping mains to Thiruvanvandoor,,Distribution for Thiruvanvandoor GP |
Contractor | J&B ENGINEERING AND CONSTRUCTION COMPANY (Mob: 9447715266) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
16 Mar 2022 | Pending | Pending | Approval/Permissions Related (from other departments excluding road cut permission and land related) | Southern Railway Chennai has objected to laying pipeline over ROB at Kallissery. | New application submitted on 03/11/2022. Joint inspection conducted with Indian railway | Action Taken |
23 Feb 2022 | Pending | 23 Feb 2022 | Road Cut Related Risk | MORTH rejection to lay pipes along side of NH 183 ( MC road) | No comments added. | Action Taken |
20 Jan 2022 | Pending | Pending | Road Cut Related Risk | MORTH not giving sanction for layting pipe line on berm of NH 183 ( Kallissery to Parayankuzhy) | No comments available. | Pending |
04 Oct 2021 | 20 Dec 2022 | Pending | Land Related Risk | Change in Location of land | Land demarcated by Taluk surveyor in same plot. | Solved |
16 Sep 2021 | Pending | Pending | Land Related Risk | Wetland conversion | Application is under process. Construction of OHSR commenced. | Action Taken |
16 Sep 2021 | Pending | 12 Jan 2022 | Land Related Risk | Wet land conversion | No comments added. | Action Taken |
09 Sep 2021 | Pending | 20 Sep 2021 | Road Cut Related Risk | Permission from Alappuzha PWD roads division to be obtained for laying pipe lines & road work in Chengannur byepass | No comments added. | Action Taken |
16 Dec 2020 | Pending | 25 Oct 2021 | Road Cut Related Risk | Permission for laying pumping main in MC road to be obtained from NH Kollam | No comments added. | Action Taken |
30 Nov 2020 | Pending | 20 Sep 2021 | Approval/Permissions Related (from other departments excluding road cut permission and land related) | Permission for laying pumping main through ROB has to be obtained from Railway | No comments added. | Action Taken |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 15/06/2021 |
---|---|
Scheduled date of Completion as per agreement | 30 Nov 2022 |
Expected date of Completion | 30/11/2023 |
TS Date | 18 Sep 2020 |
---|---|
Estimate Approval | 18 Sep 2020 |
NIT Approval | 18 Sep 2020 |
Tender Closing | 05 Oct 2020 |
Technichal Pre-Qualification | 17 Dec 2020 |
Price bid opening | 21 Dec 2020 |
Workorder Date | 04 Jan 2021 |
---|---|
NA | 16 Feb 2021 |
Adoor Project Dn AE3 |
Date: 30/04/2024 |
Work in progress | 15% Completed
Work in progress. Pile Cap work started.
Adoor Project Dn AE3 |
Date: 29/04/2024 |
Work in progress | 15% Completed
Work in progress. Pile Cap work started.