| Project | KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths-Package III(a) |
|---|---|
| Project Code | PTAKIIFB0117560P9 |
| Type | Package |
| Main Project | KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths |
| Funding Agency | KIIFB |
| Category | KIIFB | Type of scheme | Water Supply |
| Description | This package includes Construction of 15 LL-OHSR at Thiruvanvandoor,,Laying pumping mains to Thiruvanvandoor,,Distribution for Thiruvanvandoor GP |
| Status | On-going |
| District | Pathanamthitta |
| Executing Office | Adoor Project Dn |
| TS Amount (Rs) | 91950000 |
| TS Number | TS/2020-2021/2018/9295 Dated: 18-09-2020 |
| Technical specification | This package includes Construction of 15 LL-OHSR at Thiruvanvandoor,,Laying pumping mains to Thiruvanvandoor,,Distribution for Thiruvanvandoor GP |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 06/01/2021 |
|---|---|
| Scheduled date of Completion as per agreement | 30 Apr 2022 |
| Expected date of Completion | 31/03/2022 |
| TS Date | 18 Sep 2020 |
|---|---|
| Estimate Approval | 18 Sep 2020 |
| NIT Approval | 18 Sep 2020 |
| Tender Closing | 05 Oct 2020 |
| Technichal Pre-Qualification | 17 Dec 2020 |
| Price bid opening | 21 Dec 2020 |
| Workorder Date | 04 Jan 2021 |
|---|---|
| Agreement Date | 16 Feb 2021 |
| Adoor Project Dn AE2 |
| Date: 15/06/2021 |
Work in progress | 2% Completed
Entrance to site demarcated.
| Adoor Project Dn AE2 |
| Date: 14/06/2021 |
Work in progress | 2% Completed
Meeting with MLA at DC's chamber Alappuzha-MLA directed to complete the demarcation of land by15/06/2021 & work shall be started by next day itself..