| Project | JJM Paipra Providing FHTC in Paipra Panchayath |
|---|---|
| Project Code | EKMJJM08203967 |
| Type | Main project |
| Funding Agency | JJM |
| Category | JJM | Type of scheme | Water Supply |
| Description | JJM Paipra Providing FHTC in Paipra Panchayath |
| Status | On-going |
| District | Ernakulam |
| Executing Office | Muvattupuzha PH Dn |
| AS Amount (Rs) | 27000000 |
| AS Number | G.O.(Rt)No.541/2020/WRD |
| TS Amount (Rs) | 24970000 |
| TS Number | 6404/2020-2021 |
| Total Bill Submitted (Rs) | 9685804 |
| Total Bill Paid (Rs) | 9685804 |
| Population Benefitted | 18000 |
| Capacity in MLD | 0.95 |
| Actual Project Completion Date | Date is not specified |
| Coverage | Paipra Panchayat |
| Date of start of Project | Date is not specified |
|---|---|
| Scheduled date of Completion of the Project | 31 Mar 2021 |
| Expected date of Completion | 31/03/2021 |
| AS Date | 21 Aug 2020 |
|---|---|
| TS Date | 26 Aug 2020 |
| Project Officers | View |
|---|