| Project | AMRUT TSS- Laying Transmission main and sewer networks in Block J (Karimanal) Collection and Conveyance system- ( 3 packages) part 1-Trunk Main from Arasumood to Karimanal Pumping Station |
|---|---|
| Project Code | TVMAMRUT0818645P1 |
| Type | Package |
| Main Project | AMRUT TSS- Laying Transmission main and sewer networks in Block J (Karimanal) Collection and Conveyance system- ( 3 packages) |
| Funding Agency | AMRUT |
| Category | AMRUT | Type of scheme | Water Supply |
| Description | The scope includes laying HDPE pipes 500mm-205m, 630mm-1948m by HDD method and construction of manholes |
| Status | On-going |
| District | Thiruvananthapuram |
| Executing Office | Trivandrum Project Dn |
| TS Amount (Rs) | 127300000 |
| TS Number | TS/2017-2018/2018/1717 |
| Technical specification | The scope includes laying HDPE pipes 500mm-205m, 630mm-1948m by HDD method and construction of manholes. |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 27/09/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 20 Nov 2019 |
| Expected date of Completion | 31/08/2021 |
| TS Date | 26 Mar 2018 |
|---|---|
| Estimate Approval | 26 Mar 2018 |
| NIT Approval | 17 Apr 2018 |
| Tender Closing | 23 May 2018 |
| Technichal Pre-Qualification | 25 May 2018 |
| Price bid opening | 25 May 2018 |
| Workorder Date | 21 Nov 2018 |
|---|---|
| Agreement Date | 08 Feb 2019 |
| AEE5 Project TVM |
| Date: 06/07/2021 |
Work in progress | 26% Completed
Progress of the work is very poor. Now the work still pending due the lack of sufficient labors, efficient technical staff, needful machineries etc. Work done so far 17 Nos manholes,(those are partially completed) and 66m HDPE pipe laid through HDD method is totally failed. By showing the details a letter is forwarded to the contractor on 30.06.2021 (registered post). For a joining inspection on 07.06.2021 to the SE office..
| AEE5 Project TVM |
| Date: 05/07/2021 |
Work in progress | 26% Completed
Progress of the work is very poor. Now the work still pending due the lack of sufficient labors, efficient technical staff, needful machineries etc. Work done so far 17 Nos manholes,(those are partially completed) and 66m HDPE pipe laid through HDD method is totally failed. By showing the details a letter is forwarded to the contractor on 30.06.2021 (registered post). For a joining inspection on 07.06.2021 to the SE office..