AMRUT TSS- Laying Transmission main and sewer networks in Block J (Karimanal) Collection and Conveyance system- ( 3 packages) part 1-Trunk Main from Arasumood to Karimanal Pumping Station

Project AMRUT TSS- Laying Transmission main and sewer networks in Block J (Karimanal) Collection and Conveyance system- ( 3 packages) part 1-Trunk Main from Arasumood to Karimanal Pumping Station
Project Code TVMAMRUT0818645P1
Type Package
Main Project AMRUT TSS- Laying Transmission main and sewer networks in Block J (Karimanal) Collection and Conveyance system- ( 3 packages)
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Description The scope includes laying HDPE pipes 500mm-205m, 630mm-1948m by HDD method and construction of manholes
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
TS Amount (Rs) 127300000
TS Number TS/2017-2018/2018/1717
Technical specification The scope includes laying HDPE pipes 500mm-205m, 630mm-1948m by HDD method and construction of manholes.

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 27/09/2019
Scheduled date of Completion as per agreement 20 Nov 2019
Expected date of Completion 31/08/2021

Processing Dates

TS Date 26 Mar 2018
Estimate Approval 26 Mar 2018
NIT Approval 17 Apr 2018
Tender Closing 23 May 2018
Technichal Pre-Qualification 25 May 2018
Price bid opening 25 May 2018

Approval Dates

Workorder Date 21 Nov 2018
Agreement Date 08 Feb 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

AEE5 Project TVM
Date: 06/07/2021

Work in progress | 26% Completed

Progress of the work is very poor. Now the work still pending due the lack of sufficient labors, efficient technical staff, needful machineries etc. Work done so far 17 Nos manholes,(those are partially completed) and 66m HDPE pipe laid through HDD method is totally failed. By showing the details a letter is forwarded to the contractor on 30.06.2021 (registered post). For a joining inspection on 07.06.2021 to the SE office..

AEE5 Project TVM
Date: 05/07/2021

Work in progress | 26% Completed

Progress of the work is very poor. Now the work still pending due the lack of sufficient labors, efficient technical staff, needful machineries etc. Work done so far 17 Nos manholes,(those are partially completed) and 66m HDPE pipe laid through HDD method is totally failed. By showing the details a letter is forwarded to the contractor on 30.06.2021 (registered post). For a joining inspection on 07.06.2021 to the SE office..