| Project | "PACKAGE V-WSS to Patazhy,PattazhyvVadakkekara, Mylom and Thalavoor Panchayaths in Kollam district -Phase II- Distribution in Mylom panchayath" |
|---|---|
| Project Code | KLMGOK0618467P5 |
| Type | Package |
| Main Project | KIIFB-WSS to Pattazhy,Pattazhy Vadakkekkara,Mylom and Thalavoor panchayaths in Kollam District Phase II |
| Funding Agency | KIIFB |
| Category | KIIFB | Type of scheme | Water Supply |
| Description | "PACKAGE V-WSS to Patazhy,PattazhyvVadakkekara, Mylom and Thalavoor Panchayaths in Kollam district -Phase II- Distribution in Mylom panchayath" |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| TS Amount (Rs) | 185200000 |
| TS Number | TS/2019-2020/2018/11833 |
| Technical specification | PVC pipe 90mm to 160mm& DI Pipe 200mm to 350mm |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 17/03/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 16 Sep 2021 |
| Expected date of Completion | 16/09/2021 |
| TS Date | 14 Aug 2019 |
|---|---|
| Estimate Approval | 14 Aug 2019 |
| Tender Closing | 09 Oct 2019 |
| Price bid opening | 11 Oct 2019 |
| Workorder Date | 10 Mar 2020 |
|---|---|
| Agreement Date | 17 Mar 2020 |
| Kollam Project Dn EE |
| Date: 12/06/2021 |
Work in progress | 54% Completed
44.819M PIPE LAID.
| Kollam Project Dn EE |
| Date: 11/06/2021 |
Work in progress | 54% Completed
44.819M PIPE LAID.