| Project | Amruth - 2017-18-Thrissur corporation -Floating intake structure at Peechi Reservoir |
|---|---|
| Project Code | TCRAMRUT01181102P1 |
| Type | Package |
| Main Project | Amrut - 2017-18-Thrissur corporation -Floating intake structure at Peechi Reservoir |
| Funding Agency | AMRUT |
| Category | AMRUT | Type of scheme | Water Supply |
| Description | Floating intake structure at Peechi Reservoir |
| Status | On-going |
| District | Thrissur |
| Executing Office | Thrissur PH Dn |
| TS Amount (Rs) | 50000000 |
| TS Number | TS-2018-2019/2018/4452 |
| Technical specification | 1. Supply, erection, testing and commissioning of 215HP Centrifugal submersible pump. -3nos 2. 800mm DI Pipe -318m 3. 700mm DI Pipe -108m 4. 3.5x400sqmm core aluminium cable for a length of 600m 5. Pump panel room and retaining wall |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 17/08/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 26 Nov 2019 |
| Expected date of Completion | 30/09/2021 |
| TS Date | 09 May 2018 |
|---|---|
| Estimate Approval | 09 May 2018 |
| NIT Approval | 18 Sep 2018 |
| Tender Closing | 25 Sep 2018 |
| Technichal Pre-Qualification | 20 Sep 2018 |
| Price bid opening | 28 Sep 2018 |
| Workorder Date | 27 Nov 2018 |
|---|---|
| Agreement Date | 15 Dec 2018 |
| Thrissur PH Dn EE |
| Date: 15/07/2021 |
Work in progress | 60% Completed
pump set with accessories supplied,100% pipe supplied,800 mm Di -302m laid out of 318m,700mmDI 56m laid out of 108m, material of floating intake supplied, control panel board room completed, Floating intake structure assembly is in progress at Peechi Dam reservoir. Floating pontoon assembly completed. Pump and motor erection work started. Footing RCC work completed..
| Thrissur PH Dn EE |
| Date: 14/07/2021 |
Work in progress | 60% Completed
pump set with accessories supplied,100% pipe supplied,800 mm Di -302m laid out of 318m,700mmDI 56m laid out of 108m, material of floating intake supplied, control panel board room completed, Floating intake structure assembly is in progress at Peechi Dam reservoir. Floating pontoon assembly completed. Pump and motor erection work started. Footing RCC work completed..