Amruth - 2017-18-Thrissur corporation -Floating intake structure at Peechi Reservoir

Project Amruth - 2017-18-Thrissur corporation -Floating intake structure at Peechi Reservoir
Project Code TCRAMRUT01181102P1
Type Package
Main Project Amrut - 2017-18-Thrissur corporation -Floating intake structure at Peechi Reservoir
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Description Floating intake structure at Peechi Reservoir
Status On-going
District Thrissur
Executing Office Thrissur PH Dn
TS Amount (Rs) 50000000
TS Number TS-2018-2019/2018/4452
Technical specification 1. Supply, erection, testing and commissioning of 215HP Centrifugal submersible pump. -3nos 2. 800mm DI Pipe -318m 3. 700mm DI Pipe -108m 4. 3.5x400sqmm core aluminium cable for a length of 600m 5. Pump panel room and retaining wall

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 17/08/2019
Scheduled date of Completion as per agreement 26 Nov 2019
Expected date of Completion 30/09/2021

Processing Dates

TS Date 09 May 2018
Estimate Approval 09 May 2018
NIT Approval 18 Sep 2018
Tender Closing 25 Sep 2018
Technichal Pre-Qualification 20 Sep 2018
Price bid opening 28 Sep 2018

Approval Dates

Workorder Date 27 Nov 2018
Agreement Date 15 Dec 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

Thrissur PH Dn EE
Date: 15/07/2021

Work in progress | 60% Completed

pump set with accessories supplied,100% pipe supplied,800 mm Di -302m laid out of 318m,700mmDI 56m laid out of 108m, material of floating intake supplied, control panel board room completed, Floating intake structure assembly is in progress at Peechi Dam reservoir. Floating pontoon assembly completed. Pump and motor erection work started. Footing RCC work completed..

Thrissur PH Dn EE
Date: 14/07/2021

Work in progress | 60% Completed

pump set with accessories supplied,100% pipe supplied,800 mm Di -302m laid out of 318m,700mmDI 56m laid out of 108m, material of floating intake supplied, control panel board room completed, Floating intake structure assembly is in progress at Peechi Dam reservoir. Floating pontoon assembly completed. Pump and motor erection work started. Footing RCC work completed..