State plan 2020-21 Optimization of production and Transmission-Central region-Replacement of old pipe- CWSS to Kadungalloor and Alangad panchayaths- Replacing worst affected AC Pumping main from treatment plant at Muppathadam to Manjali Kunnumpuram with 250 mm DI K(9) pipe.

Project State plan 2020-21 Optimization of production and Transmission-Central region-Replacement of old pipe- CWSS to Kadungalloor and Alangad panchayaths- Replacing worst affected AC Pumping main from treatment plant at Muppathadam to Manjali Kunnumpuram with 250 mm DI K(9) pipe.
Project Code EKMGOK12206044
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Description State plan 2020-21 Optimization of production and Transmission-Central region-Replacement of old pipe- CWSS to Kadungalloor,Karumaloor and Alangad panchayaths- Replacing worst affected AC Pumping main from treatment plant at Muppathadam to Manjali Kunnumpuram with 250 mm DI K(9) pipe.
Status On-going
District Ernakulam
Executing Office Kochi WS Dn
AS Amount (Rs) 26000000
AS Number KWA/JB/P4/9/2020-21
TS Amount (Rs) 24000000
TS Number TS/2020-2021/2021/643
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 20000
Capacity in MLD 15.00
Actual Project Completion Date Date is not specified
Coverage Kadungalloor,Karumaloor and Alangad panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State plan 2020-21 Optimization of production and Transmission-Central region-Replacement of old pipe- CWSS to Kadungalloor and Alangad panchayaths- Replacing worst affected AC Pumping main from treatment plant at Muppathadam to Manjali Kunnumpuram with 250 mm DI K(9) pipe. Muppathadam WS Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Sep 2021 Estimate under scrutiny in division office Kochi WS Dn EE
16 Sep 2021 Estimate forwarded to sub division for limiting estimate amount to AS amount as per new DSoR 2018 Kochi WS Dn EE
09 Jul 2021 As per the direction of SE, Technical sanction will be issued only after receiving the Government Order vide letter from SE's office via email dtd. 22.06.2021 Kochi WS Dn EE
06 Jul 2021 As per the direction of SE, Technical sanction will be issue only after receiving the Government Order Kochi WS Dn EE
29 Jun 2021 As per the direction of SE, Technical sanction issue only after receiving the Government Order Kochi WS Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 31/10/2021

Processing Dates

AS Date 31 Dec 2020
TS Date 08 Feb 2021

Other details

Project Officers View