Project | KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths-Package IV |
---|---|
Project Code | PTAKIIFB0117560P10 |
Type | Package |
Main Project | KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | This package includes Providing new transformer & building in Kallissery WTP,RWPH kallisserry &RWPH at Kattode, upgradation of old pump house at kattod. |
Status | On-going |
District | Pathanamthitta |
Executing Office | Adoor Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 41400000 |
TS Number | TS/2020-2021/2018/7474 Dated: 17-09-2020 |
Technical specification | This package includes Providing new transformer & building in Kallissery WTP,RWPH kallisserry &RWPH at Kattode, upgradation of old pump house at kattod. |
Contractor | NIRMAN ELECTRICALS (Mob: 9447040768) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
01 Jun 2022 | Pending | Pending | Risks From Other Projects | PACKAGE 5 NEEDS TO BE COMPLEED.FOR the commissioning of this work. | No comments available. | Pending |
21 Jun 2021 | 31 Oct 2021 | 15 Sep 2021 | Approval/Permissions Related (from other departments excluding road cut permission and land related) | Soil resistivity has to be verified by EI | Soil resistivity tested | Solved |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 20/04/2021 |
---|---|
Scheduled date of Completion as per agreement | 31 Aug 2022 |
Expected date of Completion | 31/12/2023 |
TS Date | 11 Jan 2017 |
---|---|
Estimate Approval | 17 Sep 2020 |
NIT Approval | 17 Sep 2020 |
Tender Closing | 03 Nov 2020 |
Technichal Pre-Qualification | 09 Nov 2020 |
Price bid opening | 09 Nov 2020 |
Workorder Date | 01 Feb 2021 |
---|---|
NA | 15 Feb 2021 |
Adoor Project Dn AE3 |
Date: 30/04/2024 |
Work in progress | 98% Completed
Application for power allocation pending at KSEB.
Adoor Project Dn AE3 |
Date: 29/04/2024 |
Work in progress | 98% Completed
Application for power allocation pending at KSEB.