Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths-Package IV

Project KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths-Package IV
Project Code PTAKIIFB0117560P10
Type Package
Main Project KIIFB-Renovation and Augmentation of 25 mld. WTP at Kallissery and  Renovation of 33 mld WTP at Thiruvalla for Thiruvalla and Changanassery Municipalities and Adjoining Panchayths
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Description This package includes Providing new transformer & building in Kallissery WTP,RWPH kallisserry &RWPH at Kattode, upgradation of old pump house at kattod.
Status On-going
District Pathanamthitta
Executing Office Adoor Project Dn
TS Amount (Rs) 41400000
TS Number TS/2020-2021/2018/7474 Dated: 17-09-2020
Technical specification This package includes Providing new transformer & building in Kallissery WTP,RWPH kallisserry &RWPH at Kattode, upgradation of old pump house at kattod.

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 20/04/2021
Scheduled date of Completion as per agreement 14 Aug 2022
Expected date of Completion 31/03/2022

Processing Dates

TS Date 11 Jan 2017
Estimate Approval 17 Sep 2020
NIT Approval 17 Sep 2020
Tender Closing 03 Nov 2020
Technichal Pre-Qualification 09 Nov 2020
Price bid opening 09 Nov 2020

Approval Dates

Workorder Date 01 Feb 2021
Agreement Date 15 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

Adoor Project Dn AE2
Date: 15/06/2021

Work in progress | 3% Completed

Motor design submitted for approval.

Adoor Project Dn AE2
Date: 07/06/2021

Work in progress | 3% Completed

contacted LBS & CET for mix design as per the direction of TM. but they are not accepting mix design & material testing.