| Project | AMRUT Projects 2016-17 Pipe laying works Maradu Thammanam |
|---|---|
| Project Code | EKMAMRUT0917620P2 |
| Type | Package |
| Main Project | AMRUT Projects 2016-17 Pipe laying works Maradu Thammanam |
| Funding Agency | AMRUT |
| Category | AMRUT | Type of scheme | Water Supply |
| Description | AMRUT Projects 2016-17 Laying Pumping main of 500 mm DI pipe from -WTP Maradu to Pump house at Thammanam for a length of 5850 m |
| Status | On-going |
| District | Ernakulam |
| Executing Office | JnNURM Project WS Dn |
| TS Amount (Rs) | 165000000 |
| TS Number | TS/CE/CR/KWA/45/17-18 |
| Technical specification | Supplying Laying jointing testing & commissioning of 500 mm DI pipe from WTP Maradu to Pump house at Thammanam & maintaining for a period of 12 months from the date of commissioning as per the scope of KWA. |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 23/06/2018 |
|---|---|
| Scheduled date of Completion as per agreement | 22 Feb 2019 |
| Expected date of Completion | 31/12/2021 |
| TS Date | 28 Nov 2017 |
|---|---|
| Estimate Approval | 28 Nov 2017 |
| NIT Approval | 24 May 2018 |
| Tender Closing | 09 Mar 2018 |
| Technichal Pre-Qualification | 22 Mar 2018 |
| Price bid opening | 12 Mar 2018 |
| Workorder Date | 23 Jun 2018 |
|---|---|
| Agreement Date | 08 Oct 2018 |
| Kochi WS Project Dn AEE-2 |
| Date: 05/07/2021 |
Work in progress | 36% Completed
Contacted NHAI,Kochi office for follow up.
| Kochi WS Project Dn AEE-2 |
| Date: 03/07/2021 |
Work in progress | 36% Completed
A letter received from Chairman NHAI addressed to Additional Chief Secretary stating that the request for road cutting can be processed only after conducting GPR survey..