LAC- ADS- Augmentation of Kochi WSS- Improving water supply to division No. 13,14,15 & 16 of Edakochi area in Kochi Corporation - Part II- Construction of pump house and allied works
| Project |
LAC- ADS- Augmentation of Kochi WSS- Improving water supply to division No. 13,14,15 & 16 of Edakochi area in Kochi Corporation - Part II- Construction of pump house and allied works |
| Project Code |
EKMDC-LAC/ADS/SDF/KSCADC01182446 |
| Type |
Main project |
| Funding Agency |
DC-LAC/ADS/SDF/KSCADC |
| Category |
MLA ADS |
Type of scheme |
Water Supply |
| Description |
Construction of pump house and allied works -Civil works |
| Status |
On-going |
| District |
Ernakulam |
| Executing Office |
Kochi PH Dn |
| AS Amount (Rs) |
7000000
|
| AS Number |
RD5- 1369 /2017 |
| TS Amount (Rs) |
7000000 |
| TS Number |
4983/2019-20 |
| Total Bill Submitted (Rs) |
0 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
50000 |
| Capacity in MLD |
2.50 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
Kochi Corporation division 15 and 16 (New) |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
LAC- ADS- Augmentation of Kochi WSS- Improving water supply to division No. 13,14,15 & 16 of Edakochi area in Kochi Corporation - Part II- Construction of pump house and allied works |
Karuvelippady WW Sn 2 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 19 Sep 2021 |
OHSR construction work by Jnnurm team going on and only after its completion,pump house work can commence due to lack of work front
|
Kochi PH Dn EE |
|
| 14 Sep 2021 |
OHSR construction work by Jnnurm team going on and only after its completion,pump house work can commence due to lack of work front |
Kochi PH Dn EE |
|
| 10 Sep 2021 |
work can commence once OHSR construction by JNNURM team is over as work front not available.OHSR column work started |
Kochi PH Dn EE |
|
| 05 Sep 2021 |
work can commence once OHSR construction by JNNURM team is over as work front not available.OHSR column work started |
Kochi PH Dn EE |
|
| 03 Sep 2021 |
work can commence once OHSR construction by JNNURM team is over as work front not available.OHSR column work started |
Kochi PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
22/05/2020 |
| Scheduled date of Completion of the Project |
21 Sep 2020 |
| Expected date of Completion |
30/05/2022 |
Processing Dates
| AS Date |
27 Jan 2018 |
| TS Date |
01 Nov 2019 |