- KWA- Flood related work 2018 -work under...
KWA- Flood related work 2018 -work under SDRF and State plan -Replacing old&damaged (frequently bursting after flood ) 250mm ACpumping cum distribution pipe with 300mm DIpipe -new proposal through new NH from Thiniyakavu to valluvally in Kottuvally Panchayath -Unique -ID007- WSK -M-020
| Project |
KWA- Flood related work 2018 -work under SDRF and State plan -Replacing old&damaged (frequently bursting after flood ) 250mm ACpumping cum distribution pipe with 300mm DIpipe -new proposal through new NH from Thiniyakavu to valluvally in Kottuvally Panchayath -Unique -ID007- WSK -M-020 |
| Project Code |
EKMGOK01193744 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
State plan |
Type of scheme |
Water Supply |
| Description |
KWA- Flood related work 2018 -work under SDRF and State plan -Replacing old&damaged (frequently bursting after flood ) 250mm ACpumping cum distribution pipe with 300mm DIpipe -new proposal through new NH from Thoniyakavu to valluvally in Kottuvally Panchayath -Unique -ID007- WSK -M-020 |
| Status |
On-going |
| District |
Ernakulam |
| Executing Office |
Kochi WS Dn |
| AS Amount (Rs) |
24010000
|
| AS Number |
KWA/HO/OP-111/625/2018 |
| TS Amount (Rs) |
23700000 |
| TS Number |
TS/2019-2020/2019/2777 |
| Total Bill Submitted (Rs) |
0 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
15000 |
| Capacity in MLD |
63.00 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
Kottuvally Panchayath |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
KWA- Flood related work 2018 -work under SDRF and State plan -Replacing old&damaged (frequently bursting after flood ) 250mm ACpumping cum distribution pipe with 300mm DIpipe -new proposal through new NH from Thiniyakavu to valluvally in Kottuvally Panchayath -Unique -ID007- WSK -M-020 |
North Paravoor WS Sn 1 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 16 Sep 2021 |
Estimate forwarded to sub division for limiting estimate amount to AS amount as per new DSoR 2018 |
Kochi WS Dn EE |
|
| 09 Jul 2021 |
As per the direction of SE, Technical sanction will be issued only after receiving the Government Order vide letter from SE's office via email dtd. 22.06.2021 |
Kochi WS Dn EE |
|
| 06 Jul 2021 |
Estimate under verification at division office |
Kochi WS Dn EE |
|
| 29 Jun 2021 |
Estimate under verification |
Kochi WS Dn EE |
|
| 17 Jun 2021 |
Estimate for the proposed work along PWD NH road from Thonniyakavu to Mahilappady is being prepared at section office |
Kochi WS Dn EE |
|
| Review Date |
Review Message |
Review Attended By |
| 12 Jul 2021 |
The road is under DLP up to October 2021. After that road will be handed over to the PWD Roads wing. No cutting permission allowed in monsoon. Hence the request can be given to Roads Division after the DLP period |
|
Duration & Sanction dates
| Date of start of Project |
22/11/2021 |
| Scheduled date of Completion of the Project |
21 Jan 2022 |
| Expected date of Completion |
31/01/2022 |
Processing Dates
| AS Date |
17 Jan 2019 |
| TS Date |
23 Jan 2020 |