| Project |
JJM Pothanicad Providing FHTC in Pothanicad Panchayath (Circle Level) 600 connections |
| Project Code |
EKMJJM08203957 |
| Type |
Main project |
| Funding Agency |
JJM |
| Category |
JJM |
Type of scheme |
Water Supply |
| Description |
JJM Pothanicad Providing FHTC in Pothanicad Panchayath (Circle Level)
|
| Status |
On-going |
| District |
Ernakulam |
| Executing Office |
Muvattupuzha PH Dn |
| AS Amount (Rs) |
26120000
|
| AS Number |
GO(Rt) No 541/2020/WRD |
| TS Amount (Rs) |
24750000 |
| TS Number |
6880/2020-21 |
| Total Bill Submitted (Rs) |
4052469 |
| Total Bill Paid (Rs) |
4052469 |
| Population Benefitted |
2500 |
| Capacity in MLD |
1.00 |
| Actual Project Completion Date |
31 Oct 2021 |
| Coverage |
Pothanicad Panchayath |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
JM Pothanicad Providing FHTC in Pothanicad Panchayath (Circle Level) 600 connections |
Kothamangalam Sn 2 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 12 Sep 2021 |
work in progress |
Muvattupuzha PH Dn EE |
|
| 05 Sep 2021 |
117 connections given |
Muvattupuzha PH Dn EE |
|
| 24 Aug 2021 |
55 connections given |
Muvattupuzha PH Dn EE |
|
| 16 Aug 2021 |
line extension and replacement work in progress |
Muvattupuzha PH Dn EE |
|
| 09 Aug 2021 |
line extension and replacement work in progress |
Muvattupuzha PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
08/02/2021 |
| Scheduled date of Completion of the Project |
31 Mar 2021 |
| Expected date of Completion |
31/10/2021 |
Processing Dates
| AS Date |
21 Aug 2020 |
| TS Date |
07 Sep 2020 |