Deposit work of Kanhangad Municipality- Proj No 277/19- Pipeline extension to Ittammal colony
| Project |
Deposit work of Kanhangad Municipality- Proj No 277/19- Pipeline extension to Ittammal colony |
| Project Code |
KGDDEPO12207576 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
Type of scheme |
Water Supply |
| Description |
Pipeline extension |
| Status |
On-going |
| District |
Kasaragod |
| Executing Office |
Kasargod PH Dn |
| AS Amount (Rs) |
200000
|
| AS Number |
UTR No U000000769977246 |
| TS Amount (Rs) |
200000 |
| TS Number |
TS/2020-2021/2019/416 |
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
150 |
| Capacity in MLD |
0.01 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
Ittammal area |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Deposit work of Kanhangad Municipality- Proj No 277/19- Pipeline extension to Ittammal colony |
Kanhangad PH Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 04 Oct 2021 |
Status remains same. Work can be started only after Mosoon due to water logging |
Kanhangad PH Sn AE |
|
| 25 Sep 2021 |
Status remains same |
Kanhangad PH Sn AE |
|
| 21 Sep 2021 |
Status remains same. Work can start only by November due to waterlogging |
Kanhangad PH Sn AE |
|
| 14 Sep 2021 |
Status remains same |
Kanhangad PH Sn AE |
|
| 05 Sep 2021 |
Status remains same |
Kanhangad PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
14/06/2021 |
| Scheduled date of Completion of the Project |
18 Sep 2021 |
| Expected date of Completion |
30/12/2021 |
Processing Dates
| AS Date |
31 Dec 2020 |
| TS Date |
24 Feb 2021 |