AMRUT -2015-16 Improvements of coverage in Guruvayur Municipality - Laying distribution network for improvement of coverage in Pookode zone.

Project AMRUT -2015-16 Improvements of coverage in Guruvayur Municipality - Laying distribution network for improvement of coverage in Pookode zone.
Project Code TCRGOI0917533P1
Type Package
Main Project AMRUT -2015-16 Improvements of coverage in Guruvayur Municipality - Laying distribution network for improvement of coverage in Pookode zone. (Revised AS -16.67Cr)
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Description Laying Distribution network-600mm DI to 160mm PVC-41.179KM(600 mm DI-260 m,500 mm DI-794 m,450 mm DI-1109m,400 mm DI-1844m,350mm DI-111 m,300 mm DI-649 m,250mmDI-3374m,200 mm DI-6436 m,160 mm PVC-26000m)
Status On-going
District Thrissur
Executing Office Nattika Project Dn
TS Amount (Rs) 137200000
TS Number TS/CE/CR/KWA/48/17-18
Technical specification Laying Distribution network-600mm DI to 160mm PVC-41.179KM Quantity of water to be produced-7.14MLD

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 22/04/2018
Scheduled date of Completion as per agreement 05 Mar 2019
Expected date of Completion 31/03/2021

Processing Dates

TS Date 28 Nov 2017
Estimate Approval 28 Nov 2017
NIT Approval 28 Nov 2017
Supplying and Laying 28 Nov 2017
Tender Closing 23 Dec 2017
Technichal Pre-Qualification 28 Dec 2017
Price bid opening 28 Dec 2017

Approval Dates

CE Approval 02 Jan 2018
Head Office Approval 05 Mar 2018
Board Approval 05 Mar 2018
Final Approval 05 Mar 2018
Workorder Date 06 Mar 2018
Agreement Date 22 Mar 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

Nattika Project Dn AE 5
Date: 04/07/2021

Work in progress | 96% Completed

37.885 km pipe laid & interconnection works completed.96% work completed. Balance pipe to be laid in PWD common road with RWPM and CWPM.

Nattika Project Dn AE 5
Date: 02/07/2021

Work in progress | 96% Completed

37.885 km pipe laid & interconnection works completed.96% work completed. Balance pipe to be laid in PWD common road with RWPM and CWPM.