- Home
- Deposit work – RWSS to Edakkattuvayal...
Deposit work – RWSS to Edakkattuvayal Panchayath – Supplying and laying 63mm PVC pipe in Aaloor Thazham road in ward No XI Edakkattuvayal Panchayth
| Project |
Deposit work – RWSS to Edakkattuvayal Panchayath – Supplying and laying 63mm PVC pipe in Aaloor Thazham road in ward No XI Edakkattuvayal Panchayth |
| Project Code |
EKMDEPO02217603 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
Type of scheme |
Water Supply |
| Description |
Deposit work – RWSS to Edakkattuvayal Panchayath – Supplying and laying 63mm PVC pipe in Aaloor Thazham road in ward No XI Edakkattuvayal Panchayth
|
| Status |
On-going |
| District |
Ernakulam |
| Executing Office |
Muvattupuzha PH Dn |
| AS Amount (Rs) |
163000
|
| AS Number |
U000000846640512 |
| TS Amount (Rs) |
163000 |
| TS Number |
437/2021-22 |
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
Date is not specified |
| Coverage |
|
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Deposit work – RWSS to Edakkattuvayal Panchayath – Supplying and laying 63mm PVC pipe in Aaloor Thazham road in ward No XI Edakkattuvayal Panchayth |
Mulanthuruthy PH Sn 1 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 20 Sep 2021 |
Work in progress |
Muvattupuzha PH Dn EE |
|
| 15 Sep 2021 |
Work in progress |
Muvattupuzha PH Dn EE |
|
| 12 Sep 2021 |
Work in progress. |
Muvattupuzha PH Dn EE |
|
| 06 Sep 2021 |
Work in progress. |
Muvattupuzha PH Dn EE |
|
| 28 Aug 2021 |
Work in progress. |
Muvattupuzha PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
25/06/2021 |
| Scheduled date of Completion of the Project |
24 Sep 2021 |
| Expected date of Completion |
24/09/2021 |
Processing Dates
| AS Date |
24 Feb 2021 |
| TS Date |
15 Apr 2021 |