- Home
- STATE PLAN - 2019 - 20 :- RWSS TO KARUVA...
STATE PLAN - 2019 - 20 :- RWSS TO KARUVATTA- DRILLING TUBE WELL, CONSTRUCTION OF PUMP HOUSE, LAYING PUMPING MAIN, SUPPLY & ERECTION OF PUMPSET AND COMMISSIONING OF NEW SCHEME IN WARD VIII OF KARUVATTA PANCHAYAT.
| Project |
STATE PLAN - 2019 - 20 :- RWSS TO KARUVATTA- DRILLING TUBE WELL, CONSTRUCTION OF PUMP HOUSE, LAYING PUMPING MAIN, SUPPLY & ERECTION OF PUMPSET AND COMMISSIONING OF NEW SCHEME IN WARD VIII OF KARUVATTA PANCHAYAT. |
| Project Code |
ALPGOK06197900 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
State plan |
Type of scheme |
Water Supply |
| Description |
DRILLING TUBE WELL,
CONSTRUCTION OF PUMP HOUSE, LAYING PUMPING MAIN, SUPPLY &
ERECTION OF PUMPSET AND COMMISSIONING OF NEW SCHEME IN WARD
VIII OF KARUVATTA PANCHAYAT. |
| Status |
On-going |
| District |
Alappuzha |
| Executing Office |
Alappuzha PH Dn |
| AS Amount (Rs) |
1440000
|
| AS Number |
G.O.(Rt)No.419/2019/WRD |
| TS Amount (Rs) |
|
| TS Number |
|
| Total Bill Submitted (Rs) |
0 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
3000 |
| Capacity in MLD |
0.50 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
WARD 8 OF KARUVATTA PANCHAYAT |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
STATE PLAN - 2019 - 20 :- CONSTRUCTION OF PUMP HOUSE, LAYING PUMPING MAIN, SUPPLY & ERECTION OF PUMPSET AND COMMISSIONING OF NEW SCHEME IN WARD VIII OF KARUVATTA PANCHAYAT. |
Harippad PH Sn |
|
| 2 |
STATE PLAN - 2019 - 20 :- RWSS TO KARUVATTA- DRILLING TUBE WELL IN WARD VIII OF KARUVATTA PANCHAYAT. |
Harippad PH Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 09 Sep 2021 |
INVOICE RECEIVED FROM GWD SUBMITTED TO HO FOR RELEASING FUND. WORK CAN BE ARRANGED AFTER DRILLING TUBE WELL |
Harippad AE |
|
| 05 Sep 2021 |
INVOICE RECEIVED FROM GWD SUBMITTED TO HO FOR RELEASING FUND. WORK CAN BE ARRANGED AFTER DRILLING TUBE WELL |
Harippad AE |
|
| 28 Aug 2021 |
INVOICE RECEIVED FROM GWD SUBMITTED TO HO FOR RELEASING FUND. WORK CAN BE ARRANGED AFTER DRILLING TUBE WELL |
Harippad AE |
|
| 22 Aug 2021 |
INVOICE RECEIVED FROM GWD SUBMITTED TO HO FOR RELEASING FUND. WORK CAN BE ARRANGED AFTER DRILLING TUBE WELL |
Harippad AE |
|
| 16 Aug 2021 |
INVOICE RECEIVED FROM GWD SUBMITTED TO HO FOR RELEASING FUND. WORK CAN BE ARRANGED AFTER DRILLING TUBE WELL |
Harippad AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
Date is not specified |
| Scheduled date of Completion of the Project |
Date is not specified |
| Expected date of Completion |
30/11/2021 |