| Project | KIIFB project - Kasargode WSS- Replacing of old and damaged premo and PVC pipe from Vidhyanagar KWA compund to old bus stand Kasaragod (balance work)- Package1 |
|---|---|
| Project Code | KGDKIIFB01192409P1 |
| Type | Package |
| Main Project | KIIFB project - Kasargode WSS- Replacing of old and damaged premo and PVC pipe from Vidhyanagar KWA compund to old bus stand Kasaragod (balance work) |
| Funding Agency | KIIFB |
| Category | KIIFB | Type of scheme | Water Supply |
| Description | Pipe laying |
| Status | On-going |
| District | Kasaragod |
| Executing Office | Kasargod PH Dn |
| TS Amount (Rs) | 13700000 |
| TS Number | TS/2019-2020/2019/12909 |
| Technical specification | Replacing old 500 premo pipes with 500 mm DI pipes |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 11/02/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 10 Jun 2020 |
| Expected date of Completion | 31/07/2021 |
| TS Date | 13 Dec 2019 |
|---|---|
| Estimate Approval | 13 Dec 2019 |
| Tender Closing | 07 Jan 2020 |
| Price bid opening | 10 Jan 2020 |
| Workorder Date | 11 Feb 2020 |
|---|---|
| Agreement Date | 04 Mar 2020 |
| Kasargod WSP Sub Dn AEE |
| Date: 11/06/2021 |
Work in progress | 75% Completed
Work Ongoing.
| Kasargod WSP Sn AE |
| Date: 09/06/2021 |
Work in progress | 75% Completed
75% work completed,interconnection work progressing.DI pipe laying work completed..