| Project | AMRUT-WSS to Guruvayur Muncipality -Construction of steel bridge at Chirakkal for laying 600mm DI Pipe |
|---|---|
| Project Code | TCRAMRUT0917546P3 |
| Type | Package |
| Main Project | AMRUT -2016-17,2017-18 WSS to Guruvayur Municipality in Thrissur District-Improvement of water supply system for Guruvayur - Package I & II (Revised AS -81.34Cr) |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-WSS to Guruvayur Muncipality -Construction of steel bridge at Chirakkal for laying 600mm DI Pipe |
| Status | On-going |
| District | Thrissur |
| Executing Office | Nattika Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 8688637 |
| TS Number | WRD/KWA-CE(CR)/TR/8314/2022_5_1_1/1 |
| Technical specification | Construction of steel bridge at Chirakkal for laying 600mm DI Pipe |
| Contractor | Sameerali C T (Mob: 9526183333) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | Date is not specified |
| TS Date | 20 Apr 2023 |
|---|---|
| Estimate Approval | 20 Apr 2023 |
| NIT Approval | 25 Apr 2023 |
| Tender Closing | 28 Apr 2023 |
| Technichal Pre-Qualification | 02 May 2023 |
| Price bid opening | 05 May 2023 |
| Nattika Project Dn |
| Date: 18/10/2023 |
Work has been completed | 100% Completed
Work completed..
| Nattika Project Dn |
| Date: 17/10/2023 |
Work in progress | 80% Completed
Steel fabrication and pipe line works are completed. Valve fixing works are ongoing..