- Home
- DEPOSIT WORK-RWSS to Udumbanchola-Shifti...
DEPOSIT WORK-RWSS to Udumbanchola-Shifting of Water Supply pipe lines in the stretch between Udumbanchola and Chemmannar of Udumbanchola-Chithirapuram road due to road development work by KIIFB.
Project |
DEPOSIT WORK-RWSS to Udumbanchola-Shifting of Water Supply pipe lines in the stretch between Udumbanchola and Chemmannar of Udumbanchola-Chithirapuram road due to road development work by KIIFB. |
Project Code |
IDKKIIFB11219089 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
DEPOSIT WORK-RWSS to Udumbanchola-Shifting of Water Supply pipe lines in the stretch between Udumbanchola and Chemmannar of Udumbanchola-Chithirapuram road due to road development work by KIIFB. |
Status |
Completed |
District |
Idukki |
Executing Office |
Kattappana Project Dn |
AS Amount (Rs) |
14140000
|
AS Number |
KRFB-PMu/MVPA-IDK/UDMLCA-CHPM/2021 |
TS Amount (Rs) |
13440000 |
TS Number |
Order no TS/2021-22/2021/42932 |
Total Bill Submitted (Rs) |
13082048 |
Total Bill Paid (Rs) |
13082048 |
Population Benefitted |
1500 |
Capacity in MLD |
2.00 |
Actual Project Completion Date |
26 May 2022 |
Coverage |
10000 |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT WORK-RWSS to Udumbanchola-Shifting of Water Supply pipe lines in the stretch between Udumbanchola and Chemmannar of Udumbanchola-Chithirapuram road due to road development work by KIIFB. |
Project Division Kattapana |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
27/01/2022 |
Scheduled date of Completion of the Project |
26 May 2022 |
Expected date of Completion |
27/08/2022 |
Processing Dates
AS Date |
22 Nov 2021 |
TS Date |
03 Jan 2022 |