KIIFB - Augumentation of WSS To Angamaly Constituency -Part -I

Project KIIFB - Augumentation of WSS To Angamaly Constituency -Part -I
Project Code EKMKIIFB1118475
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB - Augumentation of Water Supply Schemes To Angamaly Constituency . Part I- WSS to Angamaly Muncipality, Thuravoor & Manjapra panchayaths
Status On-going
District Ernakulam
Executing Office Perumbavoor Project Dn
AS Amount (Rs) 733500000
AS Number G.O.(Rt)No.184/2018/WRD
TS Amount (Rs) 0
TS Number TS to be issued
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 87742
Capacity in MLD 17.00
Actual Project Completion Date 30 Oct 2023
Coverage Angamaly Municipality, Thuravoor & Manjapra panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB - Aug of WSS To Angamaly Constituency- PART - I Package I Project Division Perumbavoor
2 KIIFB - Aug of WSS To Angamaly Constituency- PART - I Package III Project Division Perumbavoor
3 KIIFB - Augumentation of WSS To Angamaly Constituency -Part -I Package II Project Division Perumbavoor

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Apr 2024 Part I-package 1- Tender works under progress package2-Submitted to CE(CR) for receiving approval from higher office and package 3 -Tender works under progress Perumbavoor Project Dn AE1
09 Apr 2024 Part I-package 1- Tender works under progress package2-Submitted to CE(CR) for receiving approval from higher office and package 3 -Tender works under progress Perumbavoor Project Dn AE1
04 Apr 2024 Part I-package 1- Tender works under progress package2-Submitted to CE(CR) for receiving approval from higher office and package 3 -Tender works under progress Perumbavoor Project Dn AE1
01 Apr 2024 Part I-package 1- Tender works under progress package2-Submitted to CE(CR) for receiving approval from higher office and package 3 -Tender works under progress Perumbavoor Project Dn AE1
28 Mar 2024 Part I-package 1- Tender works under progress package2-Submitted to CE(CR) for receiving approval from higher office and package 3 -Tender works under progress Perumbavoor Project Dn AE1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project 22 Nov 2022
Expected date of Completion 30/10/2023

Processing Dates

AS Date 12 Nov 2018