STATE PLAN- 2017-18- UWSS to Aluva - Replacement of old damaged 500/400mm premo pipe with 500mm DI K9 pipe from Pump Junction to Bypass and 100mm AC pipe with 160mm PVC pipe - Premo - 1.46 KM, AC - 4 KM.
| Project |
STATE PLAN- 2017-18- UWSS to Aluva - Replacement of old damaged 500/400mm premo pipe with 500mm DI K9 pipe from Pump Junction to Bypass and 100mm AC pipe with 160mm PVC pipe - Premo - 1.46 KM, AC - 4 KM. |
| Project Code |
EKMGOK05173256 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
State plan |
Type of scheme |
Water Supply |
| Description |
STATE PLAN- 2017-18- UWSS to Aluva - Replacement of old damaged 500/400mm premo pipe with 500mm DI K9 pipe from Pump Junction to Bypass and 100mm AC pipe with 160mm PVC pipe - Premo - 1.46 KM, AC - 4 KM. |
| Status |
On-going |
| District |
Ernakulam |
| Executing Office |
Aluva PH Dn |
| AS Amount (Rs) |
57500000
|
| AS Number |
G.O.(Rt) No. 1040/2017/WRD dtd. 20/12/2017 |
| TS Amount (Rs) |
57500000 |
| TS Number |
TS ORDER No. TS/2018-2019/2018/229 Dated: 26-05-2018 |
| Total Bill Submitted (Rs) |
9584879 |
| Total Bill Paid (Rs) |
9584879 |
| Population Benefitted |
40000 |
| Capacity in MLD |
10.00 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
65% |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
STATE PLAN- 2017-18- UWSS to Aluva - Replacement of old damaged 500/400mm premo pipe with 500mm DI K9 pipe from Pump Junction to Bypass and 100mm AC pipe with 160mm PVC pipe - Premo - 1.46 KM, AC - 4 KM. |
Aluva Pipeline Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 15 Sep 2021 |
Meeting was organized with MLA, Municipal chairman and the representatives from other departments and decided to start work on Sep 20th. |
Aluva AE I PL Sn |
|
| 11 Sep 2021 |
Meeting was organized with MLA, Municipal chairman and the representatives from other departments and decided to start work on Sep 20th. |
Aluva AE I PL Sn |
|
| 10 Sep 2021 |
Meeting was organized with MLA, Municipal chairman and the representatives from other departments and decided to start work on Sep 20th. |
Aluva AE I PL Sn |
|
| 07 Sep 2021 |
Balance work in pwd road can be arranged only after getting permission from PWD.PWD permission is pending due to the reason that amount for road restoration included in the esimate was not sufficient to pay the amount PWD demanded. |
Aluva AE I PL Sn |
|
| 02 Sep 2021 |
road restoration charges remitted for partial laying of pipes along PWD . Work can be started soon . The balance fund for PWD road restoration to be obtained urgently. Also awaiting fund for municipal road restoration |
Aluva AE I PL Sn |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
30/10/2018 |
| Scheduled date of Completion of the Project |
28 Feb 2019 |
| Expected date of Completion |
31/10/2021 |
Processing Dates
| AS Date |
20 Dec 2017 |
| TS Date |
26 May 2018 |