STATE PLAN- 2017-18- UWSS to Aluva - Replacement of old damaged 500/400mm premo pipe with 500mm DI K9 pipe from Pump Junction to Bypass and 100mm AC pipe with 160mm PVC pipe - Premo - 1.46 KM, AC - 4 KM.

Project STATE PLAN- 2017-18- UWSS to Aluva - Replacement of old damaged 500/400mm premo pipe with 500mm DI K9 pipe from Pump Junction to Bypass and 100mm AC pipe with 160mm PVC pipe - Premo - 1.46 KM, AC - 4 KM.
Project Code EKMGOK05173256
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Description STATE PLAN- 2017-18- UWSS to Aluva - Replacement of old damaged 500/400mm premo pipe with 500mm DI K9 pipe from Pump Junction to Bypass and 100mm AC pipe with 160mm PVC pipe - Premo - 1.46 KM, AC - 4 KM.
Status On-going
District Ernakulam
Executing Office Aluva PH Dn
AS Amount (Rs) 57500000
AS Number G.O.(Rt) No. 1040/2017/WRD dtd. 20/12/2017
TS Amount (Rs) 57500000
TS Number TS ORDER No. TS/2018-2019/2018/229 Dated: 26-05-2018
Total Bill Submitted (Rs) 9584879
Total Bill Paid (Rs) 9584879
Population Benefitted 40000
Capacity in MLD 10.00
Actual Project Completion Date Date is not specified
Coverage 65%

Packages

No. Project Name Location View
1 STATE PLAN- 2017-18- UWSS to Aluva - Replacement of old damaged 500/400mm premo pipe with 500mm DI K9 pipe from Pump Junction to Bypass and 100mm AC pipe with 160mm PVC pipe - Premo - 1.46 KM, AC - 4 KM. Aluva Pipeline Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Sep 2021 Meeting was organized with MLA, Municipal chairman and the representatives from other departments and decided to start work on Sep 20th. Aluva AE I PL Sn
11 Sep 2021 Meeting was organized with MLA, Municipal chairman and the representatives from other departments and decided to start work on Sep 20th. Aluva AE I PL Sn
10 Sep 2021 Meeting was organized with MLA, Municipal chairman and the representatives from other departments and decided to start work on Sep 20th. Aluva AE I PL Sn
07 Sep 2021 Balance work in pwd road can be arranged only after getting permission from PWD.PWD permission is pending due to the reason that amount for road restoration included in the esimate was not sufficient to pay the amount PWD demanded. Aluva AE I PL Sn
02 Sep 2021 road restoration charges remitted for partial laying of pipes along PWD . Work can be started soon . The balance fund for PWD road restoration to be obtained urgently. Also awaiting fund for municipal road restoration Aluva AE I PL Sn

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 30/10/2018
Scheduled date of Completion of the Project 28 Feb 2019
Expected date of Completion 31/10/2021

Processing Dates

AS Date 20 Dec 2017
TS Date 26 May 2018