AMRUT SAAP -2017-18 -TSS- Laying 200 mm SW sewer line in Kowdiar ward , Bhagavathi line C-15 and C-16- under Sewerage Section,Sasthamangalam
| Project |
AMRUT SAAP -2017-18 -TSS- Laying 200 mm SW sewer line in Kowdiar ward , Bhagavathi line C-15 and C-16- under Sewerage Section,Sasthamangalam |
| Project Code |
TVMAMRUT0118897P10 |
| Type |
Package |
| Main Project |
AMRUT- 2017-18- Providing new network in missing areas of core city
|
| Funding Agency |
AMRUT |
| Category |
AMRUT |
Type of scheme |
Water Supply |
| Description |
AMRUT SAAP -2017-18 -TSS- Laying 200 mm SW sewer line in Kowdiar ward , Bhagavathi line C-15 and C-16- under Sewerage Section,Sasthamangalam |
| Status |
On-going |
| District |
Thiruvananthapuram |
| Executing Office |
Pattoor Sewerage Dn |
| TS Amount (Rs) |
1540000 |
| TS Number |
112/2017-18 |
| Technical specification |
Laying 200 mm SW sewer line in Kowdiar ward , Bhagavathi line C-15 and C-16- under Sewerage Section,Sasthamangalam |
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
24/10/2018 |
| Scheduled date of Completion as per agreement |
23 Sep 2018 |
| Expected date of Completion |
04/01/2019 |
Processing Dates
| TS Date |
22 Mar 2018 |
| Estimate Approval |
22 Mar 2018 |
| NIT Approval |
05 Apr 2018 |
| Tender Closing |
13 Apr 2018 |
| Technichal Pre-Qualification |
16 Apr 2018 |
| Price bid opening |
16 Apr 2018 |
Approval Dates
| Workorder Date |
24 Apr 2018 |
| Agreement Date |
07 May 2018 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Pattoor Sewerage Dn |
| Date: 31/07/2020 |
Work has been completed | 100% Completed
completed.