| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Aug 2023 | Work Completed,Bill Submitted | Chavasseryparamba WS Sn AE | |
| 21 Jul 2023 | Work completed, bill under preparation. | Chavasseryparamba WS Sn AE | |
| 10 Jul 2023 | Work completed , Bill Under Preparation. | Chavasseryparamba WS Sn AE | |
| 01 Jul 2023 | Work Completed | Chavasseryparamba WS Sn AE | |
| 05 Aug 2023 | Bill Submitted | Chavasseryparamba WS Sn AE | |
| 21 Jul 2023 | Work Completed, bill under Preparation. | Chavasseryparamba WS Sn AE | |
| 10 Jul 2023 | Work Completed, Bill Under Preparation. | Chavasseryparamba WS Sn AE | |
| 01 Jul 2023 | Work Completed. | Chavasseryparamba WS Sn AE | |
| 30 Jun 2023 | work Progressing. | Chavasseryparamba WS Sn AE | |