letter submitted to Principal Chief Conservator of forest,TVM
Letter No.D2-1250/2020 dt.08.04.2021
KIIFB-WSS to Kodassery, Pariyaram and Athirappilly Panchayth in Thrissur District-Schematic Diagram
KIIFB-WSS to Kodassery, Pariyaram and Athirappilly Panchayth in Thrissur District-Schematic Diagram
Letter submitted by Divisional Forest Officer, Chalakudy to Principal Chief Forest Conservator, TVM
Final approval not obtained from Forest Department for constructing Intake well in the banks of Chalakudy River. Area required is 0.1143hectre. Letter submitted by Divisional Forest Officer, Chalakudy to Principal Chief Forest Conservator, TVM on 18.06.2020 (Letter No. C.A4-7330/2018) after remitting user fee and submitting Compliance report & undertaking by KWA.
Stage-1 approval for Forest Clearance
Stage-1 approval G.O.(Rt). No. 458/2019/F&WLD, Thiruvananthapuram Dated: 13.11.2019
Letter issued to Contractors by EE, Project Division, Nattika
Letter No. D1-72 PHNF dated: 15.03.2021 by EE, Project Division, Nattika. Reference:- Proceedings issued by District Collector, Thrissur No. EL1-267900/21 dated: 15.03.2021 No road cutting or trenching activities should be carried out till election process is over.
Stop memo issued by District Collector, Thrissur
Proceedings issued by District Collector, Thrissur No. EL1-267900/21 dated: 15.03.2021 No road cutting or trenching activities should be carried out till election process is over.
Technical sanction Package I
TS No.TS/2019-2020/2019/17186 Dated: 22-11-2019 Amount- Rs. 40,36,00,000.00
Administrative sanction
Order No. WRD025 - 03 - PA - 01 dated 13.11.2018 Amount - 58.61 Cr