Package: JJM- 2020-21- PHASE I- Construction of OHSR of 3LL Capacity
15/05/2021 by EE PHD KTM - 8547638555
On going | 30.00% Completed
Work on slow progress Earthworks started for R.R.M
13/05/2021 by EE PHD KTM - 8547638555
On going | 29.00% Completed
12 columns casted upto bottam of plint beam level.earth work started for R.R.M 12 columns casted upto bottam of plint beam level.earth work started for R.R.M
12/05/2021 by EE PHD KTM - 8547638555
On going | 29.00% Completed
earth work started for R.R.M 12 columns casted upto bottam of plint beam level.earth work started for R.R.M
Package: JJM- 2020-21- PHASE I-Laying pipes and providing FHTCs in Thiruvarpp Panchayath
15/05/2021 by EE PHD KTM - 8547638555
On going | 69.00% Completed
Bill under preparation Work on progress,FHTC provided 3104.
13/05/2021 by EE PHD KTM - 8547638555
On going | 68.00% Completed
Bill under preparation Work on slow progress
Package: Pipe line laying 90 mm PVC and 90 mm HDPE
15/05/2021 by EE PHD KTM - 8547638555
On going | 98.00% Completed
Bill under preparation Work on slow progress
13/05/2021 by EE PHD KTM - 8547638555
On going | 98.00% Completed
Work on progress, bill under preparation Bill under preparation
12/05/2021 by EE PHD KTM - 8547638555
On going | 98.00% Completed
work in progress work in progress