Package: KIIFB – 2017-18 Vandazhi, Kizhakkenchery, Vadakkanchery and Kannambra Panchayaths in Palakkad District – phase II - package I - Design, construction,Commissioning and Maintenance of 22.00 LL OHSR at Karimkunnam in Vadakkanchery Panchayath, Supplying and Laying 350mm DI K9 CWPM from WTP to Karimkunnam OHSR, Supplying and Erection of ,CW motor pump sets including road restoration work
29/04/2021 by AE3 - 8304000577
On going | 23.00% Completed
1.) 350mm DI pipe laid for a length of 4030.00m 2). column above plinth beam concrete work in progress. 1.) 350mm DI pipe laid for a length of 4030.00m 2). column above plinth beam concrete work in progress.