Kozhikode Project Dn AE5
Date: 22/09/2021

Work has been completed | 100% Completed

Work completed, Total expenditure Rs.47922819/- final Bill paid to contractor on 27.07.2021 including Road restoration charges .

Kozhikode Project Dn AE5
Date: 01/09/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 21/04/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 19/04/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 17/04/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 15/04/2021

Work has been completed | 100% Completed

vwork completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 12/04/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 08/04/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 07/04/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 05/04/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 03/04/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 31/03/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 27/03/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 25/03/2021

Work has been completed | 100% Completed

Work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 23/03/2021

Work in progress | 96% Completed

Work in progress

Kozhikode Project Dn AE2
Date: 18/03/2021

Work in progress | 96% Completed

Work in progress

Kozhikode Project Dn AE2
Date: 15/03/2021

Work in progress | 96% Completed

Work in progress

Kozhikode Project Dn AE2
Date: 08/03/2021

Work in progress | 95% Completed

Work in progress

Kozhikode Project Dn AE2
Date: 03/03/2021

Work in progress | 94% Completed

Work in progress

Kozhikode Project Dn AE2
Date: 23/02/2021

Work in progress | 94% Completed

work in progress

Kozhikode Project Dn AE2
Date: 16/02/2021

Work in progress | 93% Completed

work in progress road reformation, interconnection and pipeline laying work in progress

Kozhikode Project Dn AE2
Date: 05/02/2021

Work in progress | 93% Completed

Pipe line laying and road reformation works in progress

Kozhikode Project Dn AE2
Date: 26/01/2021

Work in progress | 92% Completed

Total length of pipe - 40.70 KM( 160 MM PVC-130 m, 110 MM PVC -40071 M, 100 MM GI-500 M) Pipe laid-37.53 km ,Balance to be laid 3.17 km ,Pipe laying , Road reformation and interconnection works are in progress. Quoted PAC-4.58 cr Bill Submitted-3.84cr

Kozhikode Project Dn AE2
Date: 06/01/2021

Work in progress | 90% Completed

Total length of pipe - 40.70 KM( 160 MM PVC-130 m, 110 MM PVC -40071 M, 100 MM GI-500 M) Pipe laid-36.892 km ,Balance to be laid 3.809 km ,Pipe laying , Road reformation work and interconnection works are in progress. Quoted PAC-4.58 cr Bill Submitted-2.97cr

Kozhikode Project Dn AE2
Date: 30/12/2020

Work in progress | 89% Completed

Total length of pipe - 40.70 KM( 160 MM PVC-130 m, 110 MM PVC -40071 M, 100 MM GI-500 M) Pipe laid-36.244 km ,Balance to be laid 4.457 km ,Pipe laying , Road reformation work and interconnection works are in progress. Quoted PAC-4.58 cr Bill Submitted-2.97cr

Kozhikode Project Dn AE2
Date: 10/12/2020

Work in progress | 83% Completed

Total length of pipe - 40.70 KM( 160 MM PVC-130 m, 110 MM PVC -40071 M, 100 MM GI-500 M) Pipe laid-34.169 km ,Balance to be laid 6.532 km ,Pipe laying , Road reformation work and interconnection works are in progress. Quoted PAC-4.58 cr Bill Submitted-2.97cr

Kozhikode Project Dn AE2
Date: 04/12/2020

Work in progress | 81% Completed

Total length of pipe - 40.70 KM( 160 MM PVC-130 m, 110 MM PVC -40071 M, 100 MM GI-500 M) Pipe laid-33.605 km ,Balance to be laid 7.096 km ,Pipe laying , Road reformation work and interconnection works are in progress. Quoted PAC-4.58 cr Bill Submitted-2.97cr

Kozhikode Project Dn AE2
Date: 26/11/2020

Work in progress | 76% Completed

Total length of pipe - 40.70 KM( 160 MM PVC-130 m, 110 MM PVC -40071 M, 100 MM GI-500 M) Pipe laid-32.82 km ,Balance to be laid 7.88 km ,Pipe laying , Road reformation work and interconnection works are in progress. Quoted PAC-4.58 cr Bill Submitted-2.97cr

Kozhikode Project Dn AE2
Date: 10/11/2020

Work in progress | 74% Completed

Total length of pipe - 40.70 KM( 160 MM PVC-130 m, 110 MM PVC -40071 M, 100 MM GI-500 M) Pipe laid-30 km ,Balance to be laid 10.70 km ,Pipe laying , Road reformation work and interconnection works are in progress

Attached images

img img img img img img img img img img img img img img

Kozhikode Project Dn AE2
Date: 12/10/2020

Work in progress | 69% Completed

Total length of pipe - 40.70 KM( 160 MM PVC-130 m, 110 MM PVC -40071 M, 100 MM GI-500 M) Pipe laid-27.80 KM,Balance to be laid 12.90 KM,Pipe laying , Road reformation work and interconnection works are in progress

Kozhikode Project Dn AE2
Date: 09/09/2020

Work in progress | 68% Completed

Total length of pipe - 40.70 KM( 160 MM PVC-130 m, 110 MM PVC -40071 M, 100 MM GI-500 M) Pipe already laid-26.78 KM,Balance to be laid 13.92 KM, Road reformation work and interconnection works are in progress

Attached images

img img img img img

Kozhikode Project Dn AE2
Date: 18/08/2020

Work in progress | 67% Completed

Total length of pipe - 40.70 KM( 160 MM PVC-130 m, 110 MM PVC -40071 M, 100 MM GI-500 M) Pipe already laid-26.78 KM,Balance to be laid 13.92 KM. Distribution pipe lines were already laid by PH division under various heads like SME, DRW,Deposit and MLA asset woks in the proposed locations under AMRUTH work.To avoid duplication ,this was informed in the AMRUT Core Committee meeting held on 19/5/20 and decided to arrange balance pipe line in other zones in the corporation area.Also due to heavy monsoon and Covid-19 out break ,the laying work couldnt be completed.

Kozhikode Project Dn AE2
Date: 14/08/2020

Work in progress | 66% Completed

Supplying Laying and Testing of 110mm PVC pipe for a length of 26781m out of 40071m & 100mm GI Pipe for a length of 100m out of 500m.

Kozhikode Project Dn AE2
Date: 01/07/2020

Work in progress | 65% Completed

Supplying Laying and Testing of 110mm PVC pipe for a length of 26000m out of 40071m & 100mm GI Pipe for a length of 100m out of 500m.