Kattapana AE 1
Date: 19/05/2022

Work has been completed | 100% Completed

Work is completed.

Kattappana AEE 1
Date: 18/05/2022

Work in progress | 90% Completed

Waiting For Charging work.

Kattappana AEE 1
Date: 17/05/2022

Work in progress | 90% Completed

Waiting For Charging work.

Kattapana AE 1
Date: 16/05/2022

Work in progress | 90% Completed

30m of 50mm GI Pipes laid.

Kattapana AE 1
Date: 14/05/2022

Work in progress | 84% Completed

48m of 50mm GI Pipes laid.

Kattapana AE 1
Date: 13/05/2022

Work in progress | 74% Completed

42m of 50mm GI Pipes laid.

Kattapana AE 1
Date: 12/05/2022

Work in progress | 65% Completed

48m of 50mm GI Pipes laid.

Kattapana AE 1
Date: 11/05/2022

Work in progress | 55% Completed

54m of 50mm GI Pipes laid.

Attached images

img

Kattapana AE 1
Date: 10/05/2022

Work in progress | 44% Completed

60m of 50mm GI Pipes laid.

Attached images

img

Kattapana AE 1
Date: 09/05/2022

Work in progress | 32% Completed

36m of 50mm GI Pipes laid.

Attached images

img

Kattapana AE 1
Date: 07/05/2022

Work in progress | 24% Completed

42m of 50mm GI Pipes laid.

Kattapana AE 1
Date: 03/05/2022

Work in progress | 15% Completed

Material Supply at Site