| Kattappana AEE 1 |
| Date: 29/10/2021 |
Work in progress | 80% Completed
DER for new scheme including Vandanmadu,Chakkupallam,Karunapuram and Vandiperiyar Panchayats prepared under JJM and to be submitted in 4'th SLSSC utilising some component in Vandanmedu scheme with Mullaperiyar as source.
| Kattapana AE 1 |
| Date: 25/10/2021 |
Work in progress | 80% Completed
DER for new scheme including Vandanmadu,Chakkupallam,Karunapuram and Vandiperiyar Panchayats prepared under JJM and to be submitted in 4'th SLSSC utilising some component in Vandanmedu scheme with Mullaperiyar as source.
| Kattappana AEE 1 |
| Date: 01/06/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 15/06/2021
| Kattappana AEE 1 |
| Date: 31/05/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 15/06/2021
| Kattappana AEE 1 |
| Date: 28/05/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 15/06/2021
| Kattappana AEE 1 |
| Date: 26/05/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 15/06/2021
| Kattappana AEE 1 |
| Date: 24/05/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 15/06/2021
| Kattappana AEE 1 |
| Date: 21/05/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 31/05/2021
| Kattappana AEE 1 |
| Date: 14/05/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 31/05/2021
| Kattappana AEE 1 |
| Date: 12/05/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 31/05/2021
| Kattappana AEE 1 |
| Date: 10/05/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 31/05/2021
| Kattappana AEE 1 |
| Date: 07/05/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 31/05/2021
| Kattappana AEE 1 |
| Date: 05/05/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 31/05/2021
| Kattappana AEE 1 |
| Date: 03/05/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation
| Kattappana AEE 1 |
| Date: 30/04/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation
| Kattappana AEE 1 |
| Date: 29/04/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation
| Kattappana AEE 1 |
| Date: 27/04/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation
| Kattappana AEE 1 |
| Date: 26/04/2021 |
Work in progress | 80% Completed
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation
| Kattappana AEE 1 |
| Date: 31/03/2021 |
Work in progress | 80% Completed
80% Completed
| Kattappana AEE 1 |
| Date: 25/03/2021 |
Work in progress | 80% Completed
80% Completed
| Kattappana AEE 1 |
| Date: 22/03/2021 |
Work in progress | 80% Completed
80% Completed
| Kattappana AEE 1 |
| Date: 20/03/2021 |
Work in progress | 80% Completed
80% Completed
| Kattappana AEE 1 |
| Date: 19/03/2021 |
Work in progress | 80% Completed
80% Completed
| Kattappana AEE 1 |
| Date: 09/02/2021 |
Work in progress | 80% Completed
Work of filling filter media was arranged in the risk and cost of the contractor