- Home
- Jalagramam- CWSS to Kozhijampara, Vadaka...
Jalagramam- CWSS to Kozhijampara, Vadakarapathy and Eruthenpathy Panchayaths in palakkad district -Phase I
| Project |
Jalagramam- CWSS to Kozhijampara, Vadakarapathy and Eruthenpathy Panchayaths in palakkad district -Phase I |
| Project Code |
PKDKIIFB1118675 |
| Type |
Main project |
| Category |
KIIFB |
| Description |
Package I
1. Construction of 8 MLD WTP
2. Construction of 9.8 LL OHSR
3. Supplying and laying CWPM 300 mm DI - 15570m and 150 mm DI - 1000m
Package II
Design , Construction, Commissioning and Maintenance of 11LL OHSR at Ozhalappathy in Vadakarappathy Panchayath |
| District |
Palakkad |
| Execution |
Project Division Chittur |
| AS Amount (Rs) |
237700000.00 |
| Total Bill Submitted (Rs) |
82919544.92 |
| Total Bill Paid (Rs) |
68555346.00 |
| Coverage |
kozhijampara ,vadakarapathy,Eruthempathy |
| Work Plan |
Download |
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 29 Apr 2021 |
Work in progress | 79% Completed | 29/04/2021
Kozhinjampara Plant-Filter house third floor brace beam shuttering work is in progress |
AE4 |
|
| 27 Apr 2021 |
Package-1
Work in progress | 79% Completed | 27/04/2021
Kozhinjampara Plant-Filter house Second floor Column shuttering work is in progress Pipe Gallery to Proposed sump 500 mm DI K9 pipe laying is in progress
Package-2
Floor slab concrete work complete
|
AE4 |
|
| 20 Apr 2021 |
Package-I
Work in progress | 79% Completed | 17/04/2021
Kozhinjampara plant -Filter house First floor brace beam and Wash water tank cover slab concrete is in progress Villunni River pier cap shuttering work is in progress
Package-II
Work in progress | 56% Completed | 20/04/2021
floor slab concrete work in progress
|
AE4 |
|
| 17 Apr 2021 |
Package-I
Work in progress | 79% Completed | 17/04/2021
Kozhinjampara plant -Filter house First floor brace beam and Wash water tank cover slab concrete is in progress Villunni River pier cap shuttering work is in progress
Package-II
Work in progress | 56% Completed
ozhalappathy OHSR floor slab reinforcement work in progress
|
AE4 |
|
| 17 Apr 2021 |
Work in progress | 79% Completed | 17/04/2021
Kozhinjampara plant -Filter house First floor brace beam and Wash water tank cover slab concrete is in progress Villunni River pier cap shuttering work is in progress |
AE4 |
|
No project review have been added to this project
Packages
| No. |
Project Name |
Location |
View |
| 1 |
KIIFB-2017-2018-Jalagramam–CWSSto Kozhinjampara, Vadakarapathy and Eruthempathy in Palakkad District–PhaseI-Package-I-Design, construction commissioning and maintenance of 8 MLD WTP with 6.00 LL CW sump,9.80 LLOHSR, supplying and laying 300 mm DI CWPM &150 mm DI CWPM, linking works etc |
Project Division Chittur |
|
| 2 |
KIIFB – 2017 - 2018- Jalagramam CWSS to kozhinjampara vadakarapathy and Eruthenpathy Panchayaths in Palakkad District - Phase- I- Package II - Design ,Construction commissioning and maintenance of 11.00 LL OHSR, at Ozhalapathy in vadakarapathy panchayath |
Project Division Chittur |
|
Duration & Sanction dates
| Date of Sanction |
27/11/2018 |
| Date of start |
24/06/2019 |
| Expected date of Completion |
30/06/2021 |
Other details
| Project Officers |
View |
| Funding Agency |
KIIFB |
Processing Dates
| Administrative Sanction[AS] |
27 Nov 2018 |
| Technichal Sanction[TS] |
21 Feb 2019 |
| Estimate Approval |
21 Feb 2019 |
| NIT Approval |
18 Mar 2019 |
| Supplying and Laying |
09 Jun 2020 |
| Tender Closing |
25 Mar 2019 |
| Technichal Pre-Qualification |
16 Apr 2019 |
| Price bid opening |
28 Mar 2019 |
Approval Dates
| CE Approval |
30 Apr 2019 |
| Head Office Approval |
15 Jun 2019 |
| Board Approval |
17 May 2019 |
| Final Approval |
15 Jun 2019 |
| Workorder Date |
24 Jun 2019 |
| Agreement Date |
08 Jul 2019 |