Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jalagramam- CWSS to Kozhijampara, Vadakarapathy and Eruthenpathy Panchayaths in palakkad district -Phase I

Project Jalagramam- CWSS to Kozhijampara, Vadakarapathy and Eruthenpathy Panchayaths in palakkad district -Phase I
Project Code PKDKIIFB1118675
Type Main project
Category KIIFB
Description Package I 1. Construction of 8 MLD WTP 2. Construction of 9.8 LL OHSR 3. Supplying and laying CWPM 300 mm DI - 15570m and 150 mm DI - 1000m Package II Design , Construction, Commissioning and Maintenance of 11LL OHSR at Ozhalappathy in Vadakarappathy Panchayath
District Palakkad
Execution Project Division Chittur
AS Amount (Rs) 237700000.00
Total Bill Submitted (Rs) 82919544.92
Total Bill Paid (Rs) 68555346.00
Coverage kozhijampara ,vadakarapathy,Eruthempathy
Work Plan Download

Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Apr 2021 Work in progress | 79% Completed | 29/04/2021 Kozhinjampara Plant-Filter house third floor brace beam shuttering work is in progress AE4
27 Apr 2021 Package-1 Work in progress | 79% Completed | 27/04/2021 Kozhinjampara Plant-Filter house Second floor Column shuttering work is in progress Pipe Gallery to Proposed sump 500 mm DI K9 pipe laying is in progress Package-2 Floor slab concrete work complete AE4
20 Apr 2021 Package-I Work in progress | 79% Completed | 17/04/2021 Kozhinjampara plant -Filter house First floor brace beam and Wash water tank cover slab concrete is in progress Villunni River pier cap shuttering work is in progress Package-II Work in progress | 56% Completed | 20/04/2021 floor slab concrete work in progress AE4
17 Apr 2021 Package-I Work in progress | 79% Completed | 17/04/2021 Kozhinjampara plant -Filter house First floor brace beam and Wash water tank cover slab concrete is in progress Villunni River pier cap shuttering work is in progress Package-II Work in progress | 56% Completed ozhalappathy OHSR floor slab reinforcement work in progress AE4
17 Apr 2021 Work in progress | 79% Completed | 17/04/2021 Kozhinjampara plant -Filter house First floor brace beam and Wash water tank cover slab concrete is in progress Villunni River pier cap shuttering work is in progress AE4

No project review have been added to this project

Packages

No. Project Name Location View
1 KIIFB-2017-2018-Jalagramam–CWSSto Kozhinjampara, Vadakarapathy and Eruthempathy in Palakkad District–PhaseI-Package-I-Design, construction commissioning and maintenance of 8 MLD WTP with 6.00 LL CW sump,9.80 LLOHSR, supplying and laying 300 mm DI CWPM &150 mm DI CWPM, linking works etc Project Division Chittur
2 KIIFB – 2017 - 2018- Jalagramam CWSS to kozhinjampara vadakarapathy and Eruthenpathy Panchayaths in Palakkad District - Phase- I- Package II - Design ,Construction commissioning and maintenance of 11.00 LL OHSR, at Ozhalapathy in vadakarapathy panchayath Project Division Chittur

Duration & Sanction dates

Date of Sanction 27/11/2018
Date of start 24/06/2019
Expected date of Completion 30/06/2021

Other details

Project Officers View
Funding Agency KIIFB

Processing Dates

Administrative Sanction[AS] 27 Nov 2018
Technichal Sanction[TS] 21 Feb 2019
Estimate Approval 21 Feb 2019
NIT Approval 18 Mar 2019
Supplying and Laying 09 Jun 2020
Tender Closing 25 Mar 2019
Technichal Pre-Qualification 16 Apr 2019
Price bid opening 28 Mar 2019

Approval Dates

CE Approval 30 Apr 2019
Head Office Approval 15 Jun 2019
Board Approval 17 May 2019
Final Approval 15 Jun 2019
Workorder Date 24 Jun 2019
Agreement Date 08 Jul 2019

Location