- Home
- CARWSS to Vandanmedu & Anakkara Villages
CARWSS to Vandanmedu & Anakkara Villages
| Project |
CARWSS to Vandanmedu & Anakkara Villages |
| Project Code |
IDKGOI03966053 |
| Type |
Main project |
| Funding Agency |
GOI |
| Category |
ARP Central |
| Type of scheme |
Water Supply |
| Scheme |
|
| Description |
CARWSS to Vandanmedu & Anakkara Villages |
| Status |
Short Closed |
| District |
Idukki |
| Executing Office |
Kattappana Project Dn |
| AS Amount (Rs) |
52900000
|
| AS Number |
KWA/JB/MoG/2/12-02-95 |
| TS Amount (Rs) |
51898000 |
| TS Number |
TS/CE/SR/12/95-96 |
| Total Bill Submitted (Rs) |
51898000 |
| Total Bill Paid (Rs) |
51898000 |
| Population Benefitted |
48250 |
| Capacity in MLD |
3.00 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
Vandenmedu and Anakkara Villages. Benefited population- 48250 |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
CARWSS to Vandanmedu & Anakkara Villages- Construction of 3 MLD capacity treatment plant at Nirappel City |
Project Division Kattapana |
|
| 2 |
CARWSS to Vandanmedu & Anakkara Villages- Construction of intake well cum pump house |
Project Division Kattapana |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 15 Jul 2021 |
DER submitted for new scheme utilizing the completed components with Mullaperiyar as source . |
Kattappana AEE 1 |
|
| 12 Jul 2021 |
DER prepared for new scheme utilizing the completed components with Mullaperiyar as source . |
Kattappana AEE 1 |
|
| 28 Jun 2021 |
DER prepared for new scheme utilizing the completed components with Mullaperiyar as source . |
Kattappana AEE 1 |
|
| 01 Jun 2021 |
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 15/06/2021 |
Kattappana AEE 1 |
|
| 21 May 2021 |
DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 31/05/2021 |
Kattappana AEE 1 |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
27/03/1996 |
| Scheduled date of Completion of the Project |
30 Mar 2002 |
| Expected date of Completion |
31/12/2021 |
Processing Dates
| AS Date |
12 Mar 1996 |
| TS Date |
27 Mar 1996 |