CARWSS to Vandanmedu & Anakkara Villages

Project CARWSS to Vandanmedu & Anakkara Villages
Project Code IDKGOI03966053
Type Main project
Funding Agency GOI
Category ARP Central
Type of scheme Water Supply
Scheme
Description CARWSS to Vandanmedu & Anakkara Villages
Status Short Closed
District Idukki
Executing Office Kattappana Project Dn
AS Amount (Rs) 52900000
AS Number KWA/JB/MoG/2/12-02-95
TS Amount (Rs) 51898000
TS Number TS/CE/SR/12/95-96
Total Bill Submitted (Rs) 51898000
Total Bill Paid (Rs) 51898000
Population Benefitted 48250
Capacity in MLD 3.00
Actual Project Completion Date Date is not specified
Coverage Vandenmedu and Anakkara Villages. Benefited population- 48250

Packages

No. Project Name Location View
1 CARWSS to Vandanmedu & Anakkara Villages- Construction of 3 MLD capacity treatment plant at Nirappel City Project Division Kattapana
2 CARWSS to Vandanmedu & Anakkara Villages- Construction of intake well cum pump house Project Division Kattapana

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Jul 2021 DER submitted for new scheme utilizing the completed components with Mullaperiyar as source . Kattappana AEE 1
12 Jul 2021 DER prepared for new scheme utilizing the completed components with Mullaperiyar as source . Kattappana AEE 1
28 Jun 2021 DER prepared for new scheme utilizing the completed components with Mullaperiyar as source . Kattappana AEE 1
01 Jun 2021 DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 15/06/2021 Kattappana AEE 1
21 May 2021 DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 31/05/2021 Kattappana AEE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 27/03/1996
Scheduled date of Completion of the Project 30 Mar 2002
Expected date of Completion 31/12/2021

Processing Dates

AS Date 12 Mar 1996
TS Date 27 Mar 1996

Other details

Project Officers View