CARWSS to Vandanmedu & Anakkara Villages- Construction of intake well cum pump house

Project CARWSS to Vandanmedu & Anakkara Villages- Construction of intake well cum pump house
Project Code IDKGOI03966053P1
Type Package
Main Project CARWSS to Vandanmedu & Anakkara Villages
Funding Agency GOI
Category ARP Central
Type of scheme Water Supply
Scheme
Description CARWSS to Vandanmedu & Anakkara Villages- Construction of intake well cum pump house
Status On-going
District Idukki
Executing Office Kattappana Project Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification Construction of intake well cum pump house

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/12/2000
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 15/07/2001

Processing Dates

AS Date 12 Mar 1996
TS Date 27 Mar 1996
Tender Closing 09 Dec 1999

Approval Dates

Head Office Approval 25 Aug 2000
Final Approval 25 Aug 2000
NA 01 Dec 2000

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattappana AEE 1
Date: 02/02/2021

Work has been completed | 100% Completed

Work completed on 15-07-2001.