Jal Jeevan Mission- Kasaragod District- Cheruvathur Panchayath- RWSS to Maicha and RWSS to Kadangod Phase II - Laying distribution System and providing FHTC
| Project |
Jal Jeevan Mission- Kasaragod District- Cheruvathur Panchayath- RWSS to Maicha and RWSS to Kadangod Phase II - Laying distribution System and providing FHTC |
| Project Code |
KGDJJM08202953 |
| Type |
Main project |
| Category |
JJM |
| Description |
Providing FHTC |
| District |
Kasaragod |
| Execution |
Kasargod PH Dn |
| AS Amount (Rs) |
14500000.00 |
| Total Bill Submitted (Rs) |
3092469.00 |
| Total Bill Paid (Rs) |
3092469.00 |
| Coverage |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 20 Apr 2021 |
485 FHTCs completed out of 500 Nos till date |
AE Cheruvathur |
|
| 12 Mar 2021 |
453 FHTC out of 500 FHTC completed till date . |
AE Cheruvathur |
|
| 07 Mar 2021 |
418 FHTC out of 500 FHTC completed till date ,I st part bill submitted and 3 rd party inspection comlpeted,2 nd part bill under preparation and will submit couple of days |
AE Cheruvathur |
|
| 25 Feb 2021 |
work in progress,386 FHTC already given out of 500 FHTC. Part I st bill submitted , |
EE KGD |
|
No project review have been added to this project
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Jal Jeevan Mission- Kasaragod District- Cheruvathur Panchayath- RWSS to Maicha and RWSS to Kadangod Phase II - Laying distribution System and providing FHTC- package |
Kasargod PH Dn |
|
Duration & Sanction dates
| Date of Sanction |
21/08/2020 |
| Date of start |
09/10/2020 |
| Expected date of Completion |
26/03/2021 |
Other details
| Project Officers |
View |
| Funding Agency |
JJM |
Processing Dates
| Administrative Sanction[AS] |
21 Aug 2020 |
| Technichal Sanction[TS] |
27 Aug 2020 |
Approval Dates
| Workorder Date |
15 Sep 2020 |
| Agreement Date |
05 Oct 2020 |