- Home
- NABARD RIDF-XXV-Water Supply Scheme to P...
NABARD RIDF-XXV-Water Supply Scheme to Poovar panchayath including fluoride affected areas - supplying & laying distribution net work with 300mm DI K9 to 150mm DI K9 and 110mm to 90mm PVC pipe
Project |
NABARD RIDF-XXV-Water Supply Scheme to Poovar panchayath including fluoride affected areas - supplying & laying distribution net work with 300mm DI K9 to 150mm DI K9 and 110mm to 90mm PVC pipe |
Project Code |
TVMNABARD11192682 |
Type |
Main project |
Funding Agency |
NABARD |
Category |
NABARD |
Type of scheme |
Water Supply |
Scheme |
|
Description |
1) 300 mm Dia DI K9 pipe=3970.0 m
2)250 mm Dia DI K9 pipe=3100.0m
3)200 mm Dia DI K9 pipe=5000.0m
4)150 mm Dia DI K9 pipe=545.0m
5)110 mm PVC pipe=1570.0m
6)90 mm PVC pipe=22285.0m |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
147500000
|
AS Number |
GO(RT)No.800/2019/WRD |
TS Amount (Rs) |
143200000 |
TS Number |
TS/2020-2021/2019/6202 |
Total Bill Submitted (Rs) |
5193000 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
100056 |
Capacity in MLD |
9.16 |
Actual Project Completion Date |
22 Dec 2021 |
Coverage |
Poovar Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Water Supply Scheme to Poovar panchayath including fluoride affected areas - supplying & laying distribution net work with 300mm DI K9 to 150mm DI K9 and 110mm to 90mm PVC pipe |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Nov 2023 |
Details of work done after 21-06-23 (after work restarted) FHTCs - 0 nos, 200 mm DI- 421.5. 250 DI- 1109, 90 mm PVC- 1530 m, 80 mm SLV -1 no installed |
Thiruvananthapuram Project AE2 |
|
30 Sep 2023 |
Laying works restarted from 21-06-23. The laying completed as mentioned: 90 mm- Laid for a length of 18706.95 m ( 1415 m after work restarted) 110 mm- Laid for a length of 1172.6 m 200 mm- Laid for a length of 1914.67 m 250 mm – 993.5 m |
Thiruvananthapuram Project AE2 |
|
29 Sep 2023 |
Details of work done after 21-06-23 (after work restarted) FHTCs - 0 nos, 200 mm DI- 421.5. 250 DI- 993.5, 80 mm SLV -1 no installed |
Thiruvananthapuram Project AE2 |
|
10 Jul 2023 |
Total FHTCs given- 85 nos (0 after work restarted) |
Thiruvananthapuram Project AE2 |
|
10 Jul 2023 |
Laying works restarted from 21-06-23. The laying completed as mentioned:
90 mm- Laid for a length of 17569.45 m ( 277.5 m after work restarted)
110 mm- Laid for a length of 1172.6 m
200 mm- Laid for a length of 1493.17 m
250 mm – 277.5 m (Total after work restarted)
300 mm- 0 m laid
|
Thiruvananthapuram Project AE2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/06/2021 |
Scheduled date of Completion of the Project |
22 Dec 2021 |
Expected date of Completion |
31/05/2022 |
Processing Dates
AS Date |
08 Nov 2019 |
TS Date |
29 Sep 2020 |