| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Sep 2025 | 86 Nos public tap disconnected out of 90 Nos | Kannur WS Sn AE 2 | |
| 01 Sep 2025 | 86 Nos public tap disconnected out of 90 Nos | Kannur WS Sn AE 2 | |
| 29 Aug 2025 | 86 Nos public tap disconnected out of 90 Nos | Kannur WS Sn AE 2 | |
| 25 Aug 2025 | 86 Nos public tap disconnected out of 90 Nos | Kannur WS Sn AE 2 | |
| 21 Aug 2025 | 86 Nos public tap disconnected out of 90 Nos | Kannur WS Sn AE 2 | |
| 18 Aug 2025 | 86 Nos public tap disconnected out of 90 Nos | Kannur WS Sn AE 2 | |
| 14 Aug 2025 | 86 Nos public tap disconnected out of 90 Nos | Kannur WS Sn AE 2 | |
| 06 Aug 2025 | 70 Nos public tap disconnected out of 90 Nos | Kannur WS Sn AE 2 | |
| 04 Aug 2025 | 70 Nos public tap disconnected out of 90 Nos | Kannur WS Sn AE 2 | |
| 31 Jul 2025 | 70 Nos public tap disconnected out of 90 Nos | Kannur WS Sn AE 2 |