| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Jul 2022 | road concreting work at ward 11 | Kaduthuruthy Dn EE | |
| 08 Jul 2022 | road concreting work at ward 12 | Kaduthuruthy Dn EE | |
| 07 Jul 2022 | no work | Kaduthuruthy Dn EE | |
| 06 Jul 2022 | work at ward 01 | Kaduthuruthy Dn EE | |
| 05 Jul 2022 | no work | Kaduthuruthy Dn EE | |
| 04 Jul 2022 | no work | Kaduthuruthy Dn EE | |
| 02 Jul 2022 | Interconnection work at ward 11,12 | Kaduthuruthy Dn EE | |
| 02 Jul 2022 | Pipe laying work at ward 11,12 | Kaduthuruthy Dn EE | |
| 01 Jul 2022 | Pipe laying work at ward 11,12 | Kaduthuruthy Dn EE | |
| 30 Jun 2022 | Pipe laying work at ward 11,12 | Kaduthuruthy Dn EE |