| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Jul 2021 | DER submitted for new scheme utilizing the completed components with Mullaperiyar as source . | Kattappana AEE 1 | |
| 12 Jul 2021 | DER prepared for new scheme utilizing the completed components with Mullaperiyar as source . | Kattappana AEE 1 | |
| 28 Jun 2021 | DER prepared for new scheme utilizing the completed components with Mullaperiyar as source . | Kattappana AEE 1 | |
| 01 Jun 2021 | DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 15/06/2021 | Kattappana AEE 1 | |
| 21 May 2021 | DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 31/05/2021 | Kattappana AEE 1 | |
| 12 May 2021 | DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 31/05/2021 | Kattappana AEE 1 | |
| 07 May 2021 | DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 31/05/2021 | Kattappana AEE 1 | |
| 05 May 2021 | DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation and will submit on or before 31/05/2021 | Kattappana Project Dn EE | |
| 03 May 2021 | DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation | Kattappana AEE 1 | |
| 29 Apr 2021 | DER for new scheme utilising the completed components with Mullaperiyar as source is under preparation | Kattappana AEE 1 |