| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Nov 2024 | connection work pending | Mananthavady PH Sn - AE | |
| 30 Oct 2024 | pipe laying completed | Mananthavady PH Sn - AE | |
| 23 Oct 2024 | pipe laying progress | Mananthavady PH Sn - AE | |
| 19 Oct 2024 | pipelaying progress | Mananthavady PH Sn - AE | |
| 18 Oct 2024 | Work Started. | Mananthavady PH Sn - AE | |
| 14 Oct 2024 | Pipe Supplied. | Mananthavady PH Sn - AE | |
| 09 Oct 2024 | no pipe supplied yet | Mananthavady PH Sn - AE | |
| 05 Oct 2024 | Pipe not yet supplied. | Mananthavady PH Sn - AE | |
| 01 Oct 2024 | Pipe not yet supplied. | Mananthavady PH Sn - AE | |