| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 May 2023 | Package 3 - To be re tendered after recasting the estimate in PRICE.3 | Sulthan Bathery PH Dn EE | |
| 03 May 2023 | Package 3 - To be re tendered after recasting the estimate in PRICE.3 | Kalpetta PH Sn 1 - AE | |
| 25 Apr 2023 | Package 3 - To be re tendered after recasting the estimate in PRICE.3 | Sulthan Bathery PH Dn EE | |
| 01 Mar 2023 | Package 1 & 2- completed,Package 3 - To be re tendered after recasting the estimate in PRICE.3 | Kalpetta PH Sn 1 - AE | |
| 01 Feb 2023 | Package 3 - To be re tendered after recasting the estimate in PRICE.3 | Kalpetta PH Sn 1 - AE | |
| 24 Jan 2023 | Package 3 - To be re tendered after recasting the estimate in PRICE.3 | Sulthan Bathery PH Dn EE | |
| 05 Dec 2022 | Package 1 & 2- completed,Package 3 - To be re tendered after recasting the estimate in PRICE.3 | Sulthan Bathery PH Dn EE | |
| 26 Nov 2022 | Package 1 & 2- completed,Package 3 - To be re tendered after recasting the estimate in PRICE.3 | Sulthan Bathery PH Dn EE | |
| 19 Oct 2022 | Package 3- 470 meter pipe line were laid out of 700 mater | Kalpetta PH Sn 2 - AE | |
| 17 Oct 2022 | Package 3-All the obstacles were removed and the work started again. And 400 meter pipe lines were laid out of 700 meter | Kalpetta PH Sn 2 - AE |