| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 08 Apr 2022 | Package I -99 % and package II-45% completed | Cherthala PH SUb Dn | |
| 07 Apr 2022 | Package I -99 % and package II-45% completed | Cherthala PH SUb Dn | |
| 06 Apr 2022 | Package I -99 % and package II-45% completed | Cherthala PH SUb Dn | |
| 05 Apr 2022 | Package I -99 % and package II-45% completed | Cherthala PH SUb Dn | |
| 04 Apr 2022 | FHTCs given 4104/4114 | Cherthala PH SUb Dn | |
| 02 Apr 2022 | FHTCs given 4104/4114 | Cherthala PH SUb Dn | |
| 01 Apr 2022 | FHTCs given 4104/4114 | Cherthala PH SUb Dn | |
| 31 Mar 2022 | FHTCs given 4104/4114 | Cherthala PH SUb Dn | |
| 30 Mar 2022 | FHTCs given 4104/4114, 6 Nos FHTCs pending due to private property crossing sanction | Cherthala PH SUb Dn | |
| 26 Mar 2022 | FHTCs given 4104/4114, 6 Nos FHTCs pending due to private property crossing sanction | Cherthala PH SUb Dn |