Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Sep 2022 | Final bill submitted.3512 FHTCs provided out of 4193 FHTCs | Perlasserry Sn 1 | |
30 Aug 2022 | 3512 FHTC provided out of 4193 FHTCs | Perlasserry Sn 1 | |
22 Aug 2022 | 3505 FHTC provided out of 4193 FHTCs | Perlasserry Sn 1 | |
16 Aug 2022 | 3505 FHTC provided out of 4193 FHTCs | Perlasserry Sn 1 | |
09 Aug 2022 | 3505 FHTC provided out of 4193 FHTCs | Perlasserry Sn 1 | |
04 Aug 2022 | 3505 FHTC provided out of 4193 FHTCs | Perlasserry Sn 1 | |
31 Jul 2022 | 3505 FHTC provided out of 4193 FHTCs | Perlasserry Sn 1 | |
25 Jul 2022 | 3505 FHTC provided out of 4193 FHTCs | Perlasserry Sn 1 | |
20 Jul 2022 | 3505 FHTC provided out of 4193 FHTCs | Perlasserry Sn 1 | |
17 Jul 2022 | 3500 FHTC provided out of 4193 FHTCs | Perlasserry Sn 1 |