| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Jul 2021 | 800 FHTC provided by arranging subdivision quotation. The estimate JJM works are revised as per new schedule of rate and submitted to higher authority for tendering | Kottarakkara PH Dn EE | |
| 12 Jul 2021 | 800 FHTC provided by arranging subdivision quotation. The estimate JJM works are revised as per new schedule of rate and submitted to higher authority for tendering | Kottarakkara PH Dn EE | |
| 09 Jul 2021 | 800 FHTC provided by arranging subdivision quotation. The estimate JJM works are revised as per new schedule of rate and submitted to higher authority for tendering | Kottarakkara PH Dn EE | |
| 07 Jul 2021 | 800 FHTC provided by arranging subdivision quotation. The estimate JJM works are revised as per new schedule of rate and submitted to higher authority for tendering | Kottarakkara PH Dn EE | |
| 06 Jul 2021 | 800 FHTC provided by arranging subdivision quotation. The estimate JJM works are revised as per new schedule of rate and submitted to higher authority for tendering | Kottarakkara PH Dn EE | |
| 03 Jul 2021 | 800 FHTC provided by arranging subdivision quotation. The estimate JJM works are revised as per new schedule of rate and submitted to higher authority for tendering | Kottarakkara PH Dn EE | |
| 02 Jul 2021 | 800 FHTC provided by arranging subdivision quotation. The estimate JJM works are revised as per new schedule of rate and submitted to higher authority for tendering | Kottarakkara PH Dn EE | |
| 02 Jun 2021 | Street tap based connection works onging | Kottarakkara PH Dn EE | |
| 07 Feb 2021 | Street tap based connection works onging | Kottarakkara PH Dn EE | |
| 27 Jan 2021 | No one participated. Work split up as 10 quotations and arranged the work on street tap base | Kottarakkara PH Dn EE |