Status Date Overall Project Status Project Officer Contact
15 Jun 2021 52% completed, 1223 FHTC Provided. Irinjalakkuda PH Dn EE
10 Jun 2021 VI th part bill submitted to Division office on 05.05.2021 Irinjalakkuda PH Dn EE
30 May 2021 VI th part bill submitted to Division office on 05.05.2021 Irinjalakkuda PH Dn EE
23 May 2021 VI th part bill submitted to Division office on 05.05.2021 Irinjalakkuda PH Dn EE
17 May 2021 VI th part bill submitted to Division office on 05.05.2021 Irinjalakkuda PH Dn EE
17 May 2021 VI th part bill submitted to Division office on 05.05.202 Irinjalakkuda PH Dn EE
14 May 2021 VI th part bill submitted to Division office on 05.05.2021 Irinjalakkuda PH Dn EE
05 May 2021 VI th part bill submitted to Division office on 05.05.2021 Irinjalakkuda PH Dn EE
05 May 2021 VIth part Bill submitted to Sub Division on 4.5.2021 Irinjalakkuda PH Dn EE
29 Apr 2021 49% completed, 1146 FHTC provided. Irinjalakkuda PH Dn EE