| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Jan 2025 | Work in progress | Koothuparamba Proj AE 2 | |
| 16 Jan 2025 | Final levels taken | Koothuparamba Proj AE 2 | |
| 10 Jan 2025 | Final levels taken | Koothuparamba Proj AE 2 | |
| 08 Jan 2025 | Final levels taken | Koothuparamba Proj AE 2 | |
| 04 Jan 2025 | Final levels taken | Koothuparamba Proj AE 2 | |
| 31 Dec 2024 | Final levels taken | Koothuparamba Proj AE 2 | |
| 26 Dec 2024 | Final levels taken | Koothuparamba Proj AE 2 | |
| 21 Dec 2024 | Final levels taken | Koothuparamba Proj AE 2 | |
| 18 Dec 2024 | Final levels taken | Koothuparamba Proj AE 2 | |
| 13 Dec 2024 | Final levels taken | Koothuparamba Proj AE 2 |