Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Feb 2021 | No work for few days due to contractors strike.now started | Adoor Project Dn EE | |
17 Feb 2021 | 53% work completed. | Adoor Project Dn AE2 | |
15 Feb 2021 | 265 out of 500 connections issued. | Adoor Project Dn AE2 | |
09 Feb 2021 | 245 out of 500 connections issued. | Adoor Project Dn AE2 | |
02 Feb 2021 | 236 out of 500 connections issued. | Adoor Project Dn AE2 | |
24 Jan 2021 | 202 out of 500 connections issued. | Adoor Project Dn AE2 | |
08 Jan 2021 | 153 out of 500 connections issued. | Adoor Project Dn AE2 | |
27 Dec 2020 | 116 out of 500 connections issued. | Adoor Project Dn AE2 | |
23 Nov 2020 | 32 out of 500 connections issued. | Adoor Project Dn AE2 | |