| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Mar 2025 | Tank plastering ongoing. | Kalpetta PH Sn 2 - AE | |
| 28 Feb 2025 | plastering wprk ongoing | Kalpetta PH Sn 2 - AE | |
| 17 Feb 2025 | Tank wall concrete work completed and pump house foundation concrete work completed | Kalpetta PH Sn 2 - AE | |
| 11 Feb 2025 | Tank Wall concrete second shift completed. | Kalpetta PH Sn 2 - AE | |
| 04 Feb 2025 | Tank Wall concrete completed upto 1.00m | Kalpetta PH Sn 2 - AE | |
| 29 Jan 2025 | Tank base concrete & beam concrete completed. | Kalpetta PH Sn 2 - AE | |
| 24 Jan 2025 | Pillar concrete above 3.00m completed. | Kalpetta PH Sn 2 - AE | |
| 21 Jan 2025 | Top beam,roof concrete completed. upto 3.00m above ground level. | Kalpetta PH Sn 2 - AE | |
| 17 Jan 2025 | Top beam concrete completed | Kalpetta PH Sn 2 - AE | |