| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Oct 2022 | 94% of work completed | Pullad PH Sn - AE | |
| 14 Oct 2022 | 94% of work completed | Pullad PH Sn - AE | |
| 29 Sep 2022 | 94 % WORK COMPLETED. 270 FHTCs provided out of 270.Balance work includes supply ,errection & Commissioning 2 Nos of Pumpset . | Pullad PH Sn - AE | |
| 18 Sep 2022 | 94 % WORK COMPLETED. 270 FHTCs provided out of 270.Balance work includes supply ,errection & Commissioning 2 Nos of Pumpset . | Pullad PH Sn - AE | |
| 15 Sep 2022 | 94 % WORK COMPLETED. 270 FHTCs provided out of 270.Balance work includes supply ,errection & Commissioning 2 Nos of | Pullad PH Sn - AE | |
| 31 Aug 2022 | 260 FHTCs provided out of 270FHTCs.Balance work includes supply ,errection & Commissioning 2 Nos of Pumpset | Pullad PH Sn - AE | |
| 26 Aug 2022 | 91 % completed | Pullad PH Sn - AE | |
| 23 Aug 2022 | 90 % completed | Pullad PH Sn - AE | |
| 06 Aug 2022 | 88 % completed | Pullad PH Sn - AE | |
| 19 Jul 2022 | 85 % completed | Pullad PH Sn - AE |