Status Date Overall Project Status Project Officer Contact
15 Oct 2022 94% of work completed Pullad PH Sn - AE
14 Oct 2022 94% of work completed Pullad PH Sn - AE
29 Sep 2022 94 % WORK COMPLETED. 270 FHTCs provided out of 270.Balance work includes supply ,errection & Commissioning 2 Nos of Pumpset . Pullad PH Sn - AE
18 Sep 2022 94 % WORK COMPLETED. 270 FHTCs provided out of 270.Balance work includes supply ,errection & Commissioning 2 Nos of Pumpset . Pullad PH Sn - AE
15 Sep 2022 94 % WORK COMPLETED. 270 FHTCs provided out of 270.Balance work includes supply ,errection & Commissioning 2 Nos of Pullad PH Sn - AE
31 Aug 2022 260 FHTCs provided out of 270FHTCs.Balance work includes supply ,errection & Commissioning 2 Nos of Pumpset Pullad PH Sn - AE
26 Aug 2022 91 % completed Pullad PH Sn - AE
23 Aug 2022 90 % completed Pullad PH Sn - AE
06 Aug 2022 88 % completed Pullad PH Sn - AE
19 Jul 2022 85 % completed Pullad PH Sn - AE