30 Jul 2021 | Agreement executed. Supply of pumpset delayed due to Covid. Time extension requesting letter received from contractor up to 31/08/21 | Kaduthuruthy Dn EE | |
29 Jul 2021 | Agreement executed. Supply of pumpset delayed due to Covid. Time extension requesting letter received from contractor up to 31/08/21 | Kaduthuruthy Dn EE | |
28 Jul 2021 | Agreement executed. Supply of pumpset delayed due to Covid. Time extension requesting letter received from contractor up to 31/08/21 | Kaduthuruthy Dn EE | |
26 Jul 2021 | Agreement executed. Supply of pumpset delayed due to Covid. Time extension requesting letter received from contractor up to 31/08/21 | Kaduthuruthy Dn EE | |
23 Jul 2021 | Agreement executed. Supply of pumpset delayed due to Covid. Time extension requesting letter received from contractor up to 31/08/21 | Kaduthuruthy Dn EE | |
22 Jul 2021 | Agreement executed. Supply of pumpset delayed due to Covid. Time extension requesting letter received from contractor up to 31/08/21 | Kaduthuruthy Dn EE | |
20 Jul 2021 | Agreement executed. Supply of pumpset delayed due to Covid. Time extension requesting letter received from contractor up to 31/08/21 | Kaduthuruthy Dn EE | |
19 Jul 2021 | Agreement executed. Supply of pumpset delayed due to Covid. Time extension requesting letter received from contractor up to 31/08/21 | Kaduthuruthy Dn EE | |
16 Jul 2021 | Agreement executed. Supply of pumpset delayed due to Covid. Time extension requesting letter received from contractor up to 31/08/21 | Kaduthuruthy Dn EE | |
15 Jul 2021 | Agreement executed. Supply of pumpset delayed due to Covid. Time extension requesting letter received from contractor up to 31/08/21 | Kaduthuruthy Dn EE |