| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 26 Mar 2024 | Work in progress | Punalur WS Sn - AE | |
| 19 Mar 2024 | work in progress | Punalur WS Sn - AE | |
| 15 Mar 2024 | Work In Progress | Punalur WS Sn - AE | |
| 11 Mar 2024 | work in progress | Punalur WS Sn - AE | |
| 04 Mar 2024 | Work in progress | Punalur WS Sn - AE | |
| 28 Feb 2024 | Work in progress | Punalur WS Sn - AE | |
| 22 Feb 2024 | Work in progress | Punalur WS Sn - AE | |
| 14 Feb 2024 | Work in progress | Punalur WS Sn - AE | |
| 30 Nov 2023 | Pipe supplied. Bill & road restoration amount requested to Municipality. Not recieved yet. Hence road sanction not recieved. Work pending. | Kottarakkara PH Dn EE | |
| 22 May 2023 | Work awarded | Kottarakkara PH Dn EE |