Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Nov 2024 | 2500 M PIPE PROPOSED - 700 M COMPLETED | Perlasserry Sn 1 | |
28 Oct 2024 | 2500 M PIPE PROPOSED - 700 M COMPLETED | Perlasserry Sn 1 | |
22 Oct 2024 | 700 m pipe laid out of 2500m | Perlasserry Sn 1 | |
04 Oct 2024 | Work order issued on 14-08-2024, agreement not executed. | Kannur PH Dn EE | |
03 Oct 2024 | work not started | Perlasserry Sn 1 | |
03 Oct 2024 | work not stated | Perlasserry Sn 1 | |
24 Sep 2024 | Work order issued on 14-08-2024, agreement not executed. | Kannur PH Dn EE | |
05 Sep 2024 | Work order issued on 14-08-2024. | Kannur PH Dn EE | |
29 Aug 2024 | Work order issued on 14-08-2024. | Kannur PH Dn EE | |
23 Jul 2024 | Single bid received. Tender submitted to SE for approval | Kannur PH Dn EE |